Rock Springs secures $2m HUD funding for Bitter Creek flood-control phase
City of Rock Springs, Wyoming · Meeting date: November 17, 2026 · Published: November 18, 2026
The City Council has approved a $2 million federal grant agreement for Phase 2 of the Bitter Creek Restoration Project. The funding will support engineering and construction on a downtown-adjacent reach designed to increase channel capacity and stabilise creek banks.
Key points
- Council unanimously approved the $2 million HUD Community Project Funding grant for Bitter Creek Restoration Project Phase 2, with no city match required.
- Phase 2 covers approximately one-quarter mile from the South Side Belt Bridge to the Dewar Drive Bridge and is expected to remove about 62 properties from the floodplain.
- The grant budget assigns $1.84 million to construction and $163,488 to engineering.
- Works include channel regrading, stabilised banks, retaining walls, erosion control, invasive-species removal and native and wetland replanting.
- No grant funds can be committed or drawn until HUD approves an environmental release of funds.
Full report
Rock Springs City Council has unanimously accepted a $2 million HUD Community Project Funding grant for the second phase of its Bitter Creek Restoration Project, providing federal support for flood-control works on a quarter-mile reach of the urban waterway.
Phase 2 will restore Bitter Creek between the South Side Belt Bridge and the Dewar Drive Bridge, extending roughly 250 linear feet upstream of the section covered by a 2024 appropriation. The project is intended to increase the creek’s flood-carrying capacity through channel regrading, stabilised banks, retaining walls and erosion-control measures. The city expects the work to remove approximately 62 properties from the floodplain.
The approved grant carries no local-match requirement and is budgeted at $1.84 million for construction and $163,488 for engineering. The segment is currently at 25% design.
In addition to flood-risk works, the phase includes removal of invasive vegetation and planting of native riparian, upland and wetland species. A pedestrian bridge and trail are planned to connect Dewar Drive with the future Rahonce Park and the Dewar Drive greenbelt, while providing city staff access for maintenance.
City engineering staff said the $2 million will join a previous $3.4 million appropriation for the Phase 2 segment. During the council discussion, staff confirmed that $1.8 million of the newly approved award is allocated to construction.
The project must conform to FEMA’s approved Conditional Letter of Map Revision, as well as US Army Corps of Engineers, Wyoming Department of Environmental Quality and city standards. Before it can draw or commit grant money, Rock Springs must obtain HUD’s environmental release of funds approval and complete an action plan in HUD’s Disaster Recovery Grant Reporting System. Semi-annual performance and financial reporting, along with Build America, Buy America requirements, will apply.
Phase 2 forms part of a four-phase programme intended ultimately to restore about 3.5 miles of Bitter Creek and remove 800 properties from the floodplain. Phase 1 was completed in December 2022 at a cost of $5.48 million, including $3.93 million from the Abandoned Mine Land grant programme and $1.55 million from city sources. The new HUD grant has a performance period running through 31 August 2034.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council Meeting, City of Rock Springs