Laramie redesigns 41T3 well project after bid comes in 103% over estimate
City of Laramie, Wyoming · Meeting date: November 17, 2026 · Published: November 18, 2026
Laramie City Council has approved up to $50,400 in additional engineering work to revise the 41T3 Well Piping and Treatment Project. The move follows rejection of the sole construction bid, which was about double the $2.50 million engineer’s estimate.
Key points
- Council approved Amendment 5 with Engineering Associates unanimously, 9-0.
- The amendment provides $35,400 in additional services plus a $15,000 contingency, within a total professional-services contract authority of $315,400.
- The sole August construction bid exceeded the $2,501,802 engineer’s estimate by about 103%; council rejected all bids in September.
- The project is intended to bring a drilled groundwater well into service through pump installation, treatment works and a distribution-system connection.
Full report
Laramie City Council has authorised further redesign work on its 41T3 municipal well project after the only construction bid received for the scheme exceeded the engineer’s estimate by approximately 103%.
Council voted 9-0 on November 17 to approve Amendment 5 to its professional-services agreement with Engineering Associates. The amendment authorises $35,400 of additional work and a $15,000 contingency, with the overall professional-services contract capped at $315,400.
The decision is intended to restart a project that would add a new groundwater source to the city’s water system. The 41T3 well has already been drilled. Remaining works include pump installation, a treatment facility and piping to connect the source to Laramie’s distribution system.
Bids for the piping and treatment phase were opened on August 4. Only one was received, and it came in about 103% above the $2,501,802 engineer’s construction estimate. Council subsequently approved Resolution 2026-54 in September rejecting all bids.
The new Engineering Associates scope covers updated wellhead-building plans and specifications, structural and electrical coordination, revisions to bidding documents, and additional design and bidding services. Staff said the work is intended to reassess the project scope, pursue construction cost savings and improve bid competitiveness before the project is advertised again.
The consultant’s amendment describes the redesign as incorporating substantial cost-saving changes to the wellhead building. Supporting cost information includes revisions to building-design sheets, review of process and instrumentation diagrams, structural and electrical/mechanical design work, surveying, updates to the project manual, a revised cost estimate, bidder-question support, a pre-bid meeting and bid review.
The project is funded through Laramie’s Water Fund. In presenting the amendment, staff described bringing a new groundwater source into service as an infrequent but significant addition to the city’s available supply.