Mequon raises sewer charges as $9.85m capital programme takes shape
City of Mequon, Wisconsin · Meeting date: November 10, 2026 · Published: November 11, 2026
Mequon Common Council has approved a 2.0% increase in the quarterly flat sewer charge and a 2.5% rise in volumetric rates for 2027. The rate action accompanies a $9.85 million sewer capital programme, dominated by work at Ranch Road Lift Station E and system-control upgrades.
Key points
- The 2027 quarterly flat sewer charge will rise from $90 to $92, while the volumetric rate will increase from $8.811 to $9.028 per 1,000 gallons.
- The council retained the sewer district levy at $7.263 million, including $3.867 million for the net MMSD capital charge, $1.666 million for city debt service and $1.731 million for capital improvements.
- The 2027 capital plan totals $9.855 million, of which $7.911 million is earmarked for Ranch Road Lift Station E construction.
- The council also authorised spending above $25,000 with five contractors for sewer lateral, emergency repair, electrical and rehabilitation work.
Full report
Mequon Common Council has approved 2027 sanitary sewer rates that lift the quarterly flat charge to $92 and the volumetric charge to $9.028 per 1,000 gallons, while maintaining the utility district's $7.263 million annual levy.
The flat charge rises 2.0% from $90 in 2026, while the volumetric charge rises 2.5% from $8.811 per 1,000 gallons. The city also set a tax-exempt capital rate of $11.38 per 1,000 gallons, unchanged from 2026. Residential non-water accounts are billed on the flat quarterly charge, while residential water and non-residential accounts are charged on metered volume.
The rate package supports a 2027 sewer capital programme of $9.855 million. Its principal component is $7.911 million for construction of the Ranch Road Lift Station E replacement. The utility's objectives for the year include bringing the new station online and decommissioning the existing facility, as well as installing Heritage Estates gravity sewer upgrades before the new station enters service.
Other 2027 capital allocations include $997,525 for SCADA software, radios and computers; $150,000 for condition-assessment implementation at lift stations; $150,000 for design of Glen Oaks Lane Area E gravity sewer improvements; and $300,000 for equipment replacement. The plan also includes flow monitoring, lift-station metering, a flow-meter audit and GIS sewer-lateral tools.
The approved user-rate calculation identifies $2.060 million of MMSD operation and maintenance charges, $1.408 million of Mequon operation and maintenance costs, and $1.180 million of self-funded capital as the principal volumetric-rate components. Projected annual flow is 514.849 million gallons, including 310.849 million gallons from 7,623 residential customers and 204 million gallons from 449 commercial customers.
Mequon's approved sewer levy remains at $7.263 million. The allocation includes $3.867 million for the estimated net MMSD capital charge, $1.666 million for city capital debt service and $1.731 million for sewer capital improvements. The estimated MMSD capital charge before adjustments is $4.414 million, 8.5% above the amount invoiced in 2026. City debt service is associated with the East Trunk Sewer project, funded through $19.4 million of general-obligation bonds issued in 2018.
The 2027 budget projects a debt-service coverage ratio of 2.71, compared with the utility policy's recommended 1.6 ratio. Staff said that reaching the recommended level immediately would require a significant rate increase, conflicting with the policy objective of stable user-rate adjustments.
Separately, the council authorised the utility to exceed its $25,000 annual vendor threshold with Budiac Plumbing, D.F. Tomasini Contractors, Frank D. Gilitzer Electric, Grunau Company and Visu-Sewer. The firms may be used for non-capital lateral repairs and excavation, emergency repairs, lift-station electrical work, and sewer rehabilitation work, subject to the city's purchasing policy.