Essex readies $3.6m Fort Ethan Allen water-main bond push
Town of Essex, Vermont · Meeting date: November 16, 2026 · Published: November 17, 2026
The first contract in Essex's three-part Fort Ethan Allen Waterline Project would replace roughly 4,000ft of main, water services and hydrants. The town is eligible for a 30-year, 2% Drinking Water State Revolving Fund loan, but must meet early-2027 bond-vote deadlines to use the financing.
Key points
- Contract 1 is estimated at $3.6 million, including construction, a 10% contingency, engineering, permits and short-term interest.
- The works cover Barnes Avenue and the southwestern halves of Hegeman and Ethan Allen Avenues, replacing around 4,000ft of water main.
- Services and curb stops will be replaced to the right-of-way, with full service replacements where lead or galvanized pipe is found.
- Final design is complete; most permits have been received, while an Act 250 permit and a Town of Colchester excavation permit remain outstanding.
- Staff will return to the Selectboard in December to discuss funding options and a potential bond vote.
Full report
Essex is moving toward a financing decision for the first $3.6 million phase of its Fort Ethan Allen Waterline Project, as completed design work and prospective state revolving-fund financing bring a bond vote into focus.
Contract 1 would replace approximately 4,000 linear feet of water main along Barnes Avenue and the southwestern halves of Hegeman and Ethan Allen Avenues. The scope also includes replacing water services and curb stops to the edge of the right-of-way. Where lead or galvanized service materials are encountered, the town plans full replacement of the service line.
The project also provides for fire-hydrant replacements, surface restoration and management of contaminated soils described as widespread across the site.
Essex estimates the contract at $3.6 million, covering construction, a 10% construction contingency, engineering and miscellaneous costs including permit fees and short-term interest. It is listed in the fundable range of the Drinking Water State Revolving Fund Intended Use Plan and is eligible for a 30-year loan at 2% interest.
Accessing that funding requires the town to schedule a bond vote before January 31, 2027, and to pass the vote before May 1, 2027. Staff plan to bring funding options and a potential Town Meeting bond vote back to the Selectboard at its first December meeting.
Final design for Contract 1 is complete. Most permits have been received, although an Act 250 permit was expected within weeks and the Town of Colchester excavation permit will be sought closer to construction. The town attorney was expected to provide draft construction-easement agreements, after which engineering and town staff will seek signatures from affected Fort Ethan Allen residents.
The works are the first of three planned contracts for the Fort Ethan Allen area. Water-main replacements covered by Contracts 2 and 3 are intended for future planning and are not part of the current project.
This summary was generated by AI based on the source document and may contain errors.