Pleasant Grove adopts $201.8m water plan as aquifer pressure mounts
Pleasant Grove City, Utah · Meeting date: November 17, 2026 · Published: November 18, 2026
Pleasant Grove, Utah, has approved a long-range culinary-water capital programme that combines distribution upgrades, storage additions and system replacement with a framework for allocating growth-related costs through impact fees. The plan identifies groundwater over-allocation, drought and higher-density development as challenges to meeting future supply needs.
Key points
- The unanimously adopted culinary-water plan sets out $201.76 million of expenditures through 2050, including $18.98 million classified as impact expense and $182.78 million as operating expense.
- Near-term works include North Field Zone pressure-reducing valves, waterline upsizing, 4-inch waterline replacement and the first instalments of buildout distribution piping; a Cedar Hills tank addition is scheduled for 2027-28.
- The plan says North Utah County water rights have been over-allocated and aquifer levels have dropped significantly in recent drought years; it recommends aquifer-storage-and-recovery participation, conservation and leak detection.
- Council also unanimously adopted updated sanitary sewer, stormwater and pressurized-irrigation master plans and impact-fee facility plans.
Full report
Pleasant Grove City Council has adopted a $201.76 million culinary-water investment programme through 2050, setting a new planning and impact-fee framework as the Utah utility confronts distribution deficiencies, projected growth and mounting uncertainty over groundwater supply.
The unanimously approved 2026 Culinary Water System Master Plan and Impact Fee Facility Plan identifies $22.00 million of current system deficiencies, including $10.11 million for 4-inch waterline replacement, $7.43 million for waterline upsizing, $3.29 million for a Cedar Hills tank addition, $825,300 for North Field Zone pressure-reducing valves and $338,408 for new 8-inch loop connections. A further $20.26 million of buildout projects comprises $11.28 million of distribution and transmission piping and an $8.98 million Monson tank addition.
The programme’s full 2025-50 schedule totals $201.76 million in 2025 dollars. Of that amount, $18.98 million is identified as impact expense and $182.78 million as operating expense. The schedule begins with North Field Zone PRVs, waterline upsizing, 4-inch main replacement, system replacement and buildout piping. The Cedar Hills tank addition is scheduled for fiscal 2027-28, while the Monson tank is scheduled in fiscal 2026-27 and 2028-29 instalments.
Director Neal Winterton told the council that the master plans establish a starting point for a continually updated model of utility needs, rather than a fixed construction commitment. The models are intended to test present capacity and future demand, identify priorities and support coordination with road, sewer, stormwater and irrigation works. He said the city will subsequently engage a consultant for an impact-fee analysis, which will determine charges to new connections for growth-related infrastructure.
The culinary-water plan projects the city’s population will rise from 39,604 in 2025 to 53,000 by 2050. It warns that the city obtains most of its drinking water from wells tapping the North Utah County aquifer, a share expected to rise at buildout. The state engineer has determined that water rights in North Utah County are over-allocated, the plan says, while drought years have contributed to significant declines in aquifer levels.
The plan calls for the city to participate in aquifer storage and recovery efforts, remain active in the North Utah County Aquifer Council, continue conservation and leak-detection work, and replace ageing infrastructure to reduce losses from leaks and breaks. It also states that surface-water treatment using American Fork River or Provo River supplies could be necessary in the future if groundwater cannot meet the city’s needs.
Council approved three companion utility plans at the same meeting. The stormwater plan includes $68.79 million of planned expenditures through 2050, the sanitary-sewer plan includes $46.56 million, and the pressurized-irrigation plan totals $17.90 million. The latter includes a $12.34 million Mill Ditch piping project, which staff described as a long-term, potential future project to be pursued section by section if funding becomes available.
Winterton said the four master plans will be used to distinguish infrastructure needed for existing customers from capacity required by growth, allowing the city to assign the growth-related component to impact-fee funding.
This summary was generated by AI based on the source document and may contain errors.