Tyler advances Blackfork Creek drainage upgrades with $469k design awards
Tyler Water Utilities, Texas · Meeting date: November 18, 2026 · Published: November 19, 2026
The city approved two work orders for Elledge Engineering Corp. covering design through construction-phase services for culvert projects around Hillside Park and the High and Saunders avenue crossings. The schemes address deteriorated infrastructure and road overtopping during major storm events.
Key points
- Council approved a $180,000 work order for Hillside Park Culvert Rehabilitation, including replacement of about 200 linear feet of deteriorated concrete top slab and measures to increase capacity.
- A separate $289,000 work order will design replacement culverts and raised roadways at High and Saunders avenues, where 100-year flooding is projected to overtop the roads by 2.85 feet and 2.41 feet, respectively.
- Both assignments went to Elledge Engineering Corp. under its master services agreement for drainage improvements and include surveying, bidding support, construction engineering and observation.
- Design schedules target bid phases by April 2027, with construction engineering and observation extending into 2028.
Full report
Tyler City Council has approved $469,000 in engineering work to move forward two stormwater schemes on Blackfork Creek tributaries, targeting a deteriorated culvert beneath Hillside Park and flood-prone road crossings immediately upstream.
Elledge Engineering Corp. received a work order not to exceed $180,000 for design, bidding, surveying and construction-phase services for the Hillside Park Culvert Rehabilitation project. The scheme covers the drainage structure beneath the park’s soccer field and includes replacement of approximately 200 linear feet of concrete top slab, repairs to erosion at the wall bottoms, resurfacing and sealing of the floor slab, and construction of a junction intended to increase capacity.
City staff said exposed reinforcing steel and other deterioration made rehabilitation necessary. The engineering scope will also assess an upstream channel configuration intended to straighten stormwater flow into the culvert. The city is targeting construction during the summer, when the soccer field has less use.
The council also authorized a separate work order, capped at $289,000, for replacement culverts at High and Saunders avenues. The crossings lie south of East Erwin Street and serve routes near Bonner Elementary; Saunders Avenue also continues south across Front Street toward the hospital district.
The project is intended to replace undersized culverts and raise both roadways so that water does not enter the roads during a 100-year event. Preliminary analysis cited by the city projects existing 100-year overtopping of 2.85 feet at High Avenue and 2.41 feet at Saunders Avenue. Initial engineering indications point to raising High Avenue by about 3.5 to 4 feet and Saunders Avenue by about 3 to 3.5 feet at the crossings, subject to design.
The Saunders Avenue work will need to account for an existing 6-inch water line and protect a recently constructed 30-inch sewer main located about one foot below the flowline of the existing culvert. Preliminary recommendations call for four-barrel 10-foot-by-9-foot box culverts at both crossings, with further study required on water-surface effects.
Both work orders are part of the 2027 Half-Cent Sales Tax Annual Work Program. Bid phases for each project are scheduled for April 2027.