Texas approves $34m for Marble Falls floodway wastewater plant relocation
Texas Water Development Board, Texas · Meeting date: November 12, 2026 · Published: November 16, 2026
The Texas Water Development Board has approved $34 million in Clean Water State Revolving Fund assistance for Marble Falls to continue construction of a new wastewater reclamation plant outside the existing floodway. The project will double treatment capacity from 1.5 MGD to 3.0 MGD.
Key points
- Marble Falls received $34 million in Clean Water State Revolving Fund assistance for wastewater-system construction.
- The city is relocating its wastewater treatment and reclamation plant from the existing floodway after flooding during major events over the past decade.
- The new facility is being expanded to 3.0 MGD as the city responds to continued population growth.
- The board described the overall project as a $120 million investment for a community with fewer than 10,000 residents.
Full report
The Texas Water Development Board has approved $34 million in Clean Water State Revolving Fund assistance for Marble Falls to continue construction of a wastewater treatment and reclamation plant outside its existing floodway.
The funding addresses additional construction costs on a project that combines flood resilience with added treatment capacity. Marble Falls, about 45 miles west of Austin, serves a population of 9,500 through roughly 3,500 water and wastewater connections. Its existing wastewater plant has flooded during major events over the past decade.
The city previously secured Flood Infrastructure Fund and Clean Water State Revolving Fund support to relocate and build the new reclamation plant. Continued population growth has led Marble Falls to increase the proposed plant capacity from 1.5 million gallons per day to 3.0 MGD.
The works include a new lift station and force main, treatment and disinfection processes, a drainage pump station, biosolids handling and SCADA. Board staff said the additional assistance is needed because construction costs were higher than expected.
Board members framed the award as a significant intervention for a small utility. One director described the scheme as a $120 million project for a service population of less than 10,000, saying this scale of investment would be difficult for the community to bear independently.
The approval provides the requested construction funding to continue the wastewater plant project, which the city said will support its One Water initiative and a sustainable water future.
This summary was generated by AI based on the source document and may contain errors.
Source: Board Meeting, Texas Water Development Board