Texarkana commits $1.49m to wastewater plant and sewer upgrades
Texarkana Water Utilities, Texas · Meeting date: November 9, 2026 · Published: November 10, 2026
Texarkana Water Utilities will award contracts to RBIS and Kampco for a combined $1.486m of treatment-plant structural work and sewer-collection infrastructure. The two projects were approved as part of the City Council's consent calendar on 9 November.
Key points
- RBIS, LLC won a $554,320 contract for structural improvements covering both treatment units at the Waggoner Creek WWTP.
- Kampco, Inc. was awarded a $931,801.36 contract for Phase II replacement of the Beaumont 15-inch sewer project on Beaumont and Caddo streets.
- The sewer project includes 1,800ft of 8-inch pipe, 13 manholes, a lift station and 1,100ft of 2-inch force main.
- Funding is budgeted through the Waggoner Creek Capital Improvement Fund and the Texas Infrastructure Improvement Fund.
Full report
Texarkana City Council has authorised almost $1.49m of wastewater investment, approving contracts for repairs at the Waggoner Creek wastewater treatment plant and a sewer-collection upgrade serving Beaumont Street and Caddo Street.
The larger award, valued at up to $931,801.36, goes to Kampco, Inc. of Texarkana, Arkansas, for the Replace Beaumont 15-Inch Sewer Phase II project. The scheme will install 1,800ft of 8-inch sewer pipe, 13 manholes, one lift station and 1,100ft of 2-inch sewer force main, together with associated works.
Kampco submitted the lowest of three bids received on 20 October. RBIS, LLC bid $997,138, while TriState Sitework submitted a $1.075m bid. The contract is funded through Texarkana Water Utilities' 2026-27 Texas Infrastructure Improvement Fund.
The council also approved a $554,320 contract with RBIS, LLC of Texarkana, Texas, for structural improvements to both treatment units at the Waggoner Creek WWTP. The work covers fabrication and installation of replacement steel columns, supports, catwalks and other steel components. Bid documents specify replacement wastewater troughs, catwalk systems, air drops and steel plate.
RBIS was the lower of two bidders for the treatment-plant work, undercutting Flowers Construction's $997,996 proposal by $443,676. A.L. Franks Engineering recommended that the utility proceed with the full two-unit scope, rather than work limited to the east-side treatment unit, which had been priced at $277,160 by RBIS.
The Waggoner Creek contract will be paid from the utility's 2026-27 Waggoner Creek Capital Improvement Fund. Both wastewater contracts were included in the consent calendar, which the council approved without pulling either item for separate discussion.
The paired awards address infrastructure at two points in the wastewater system: treatment-unit structural components at Waggoner Creek and new gravity sewer, force-main and lift-station assets in the Beaumont and Caddo Street area.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council Meeting, Texarkana Water Utilities