NTMWD targets $106m PFAS settlements to fund $91m treatment upgrade
North Texas Municipal Water District, Texas · Meeting date: November 19, 2026 · Published: November 20, 2026
North Texas Municipal Water District has received more than $82 million of an expected $106 million in PFAS settlement proceeds. The utility is designing a $91 million advanced-treatment project associated with its Tawakoni water supply, with construction completion targeted for 2029.
Key points
- NTMWD expects about $106 million from settlements with PFAS manufacturers, including estimates for the newly announced Carrier, Amorex, Arcroma and Nation Ford settlements and a special-needs claim.
- More than $82 million, or about 78% of the expected total, has already been received and is being held in a dedicated account for PFAS-related district costs.
- The district is at 60% design on a granular activated carbon project with an estimated $91 million capital cost; design is expected to finish in spring 2027, followed by bidding and award in summer.
- The project is intended to ensure compliance with the US EPA's four-parts-per-trillion limit for PFOA and PFOS by 2029.
- The board also approved $5.4 million for right-of-way acquisition on the Leonard-to-Princeton treated-water pipeline.
Full report
North Texas Municipal Water District is positioning settlement recoveries from PFAS manufacturers to cover the capital cost of new drinking-water treatment, with more than $82 million already received from an expected total of approximately $106 million.
The district told its board on 19 November that it is holding the proceeds in a dedicated account specifically for future PFAS costs. The projected total is sufficient to broadly match the current $91 million estimate for a granular activated carbon treatment project associated with the Tawakoni water supply.
The project is at 60% design. Design completion is expected in spring 2027, with bidding and award planned for the summer and construction completion targeted in 2029. The presentation described installation of the granular activated carbon treatment at the Wylie Water Treatment Plant as part of the Tawakoni treatment upgrades.
The scheme is intended to comply with the US Environmental Protection Agency's drinking-water limit of four parts per trillion for PFOA and PFOS, two compounds within the wider PFAS group. The compliance test is based on an annual average rather than an individual sample. District staff said the treatment design is being sized to maintain compliance under varying source-water conditions, including drought.
The settlement programme began with agreements announced by 3M and DuPont in 2023, followed by BASF and TICO. NTMWD opted into the earlier settlements and has submitted claims under their various payment phases. The 3M settlement provides payments over time, with the remaining 25% due through 2033, while the other settlements are structured as lump-sum payments.
Four additional manufacturers — Carrier, Amorex, Arcroma and Nation Ford — have recently announced settlements. NTMWD will remain in that class by taking no action before the December opt-out deadline, then pursue claims when the process and deadlines are announced. Estimated receipts from that group and from a special-needs claim remain uncertain; all other figures have been confirmed through the claims process.
The district completed a PFAS roadmap in 2025 assessing its water and wastewater systems. It concluded that treatment upgrades were needed at Tawakoni, while no other facility improvements were then recommended. Monitoring will continue at other sources and at wastewater facilities to determine whether conditions change. Staff said current data did not justify treatment investment elsewhere, although potential locations for future additional treatment have been identified in master planning for the Wylie complex.
NTMWD has also applied for Texas Water Development Board grant funding through the Drinking Water State Revolving Fund and was recently invited to reapply. Any grant proceeds would be used first to offset capital costs, with settlement funds then applied to remaining PFAS obligations.
Separately, the board approved a $5.4 million right-of-way acquisition programme for the Leonard-to-Princeton treated-water pipeline. The resolution authorises acquisition of permanent, temporary-construction and access easements, and delegates authority to initiate condemnation proceedings if negotiations fail after a final offer letter has been issued. The pipeline is intended to meet projected water demand in the district's north and east systems.
This summary was generated by AI based on the source document and may contain errors.
Source: Board of Directors, North Texas Municipal Water District