Killeen delays tripling of water impact fee for stakeholder review
City of Killeen Water & Sewer Department, Texas · Meeting date: November 17, 2026 · Published: November 18, 2026
Killeen has postponed until 8 December its decision on a maximum water and wastewater impact-fee schedule that would raise the combined charge on a standard ¾-inch connection from $1,579 to $4,844. The delay gives staff time to meet stakeholders and return with responses on alternatives including phased charges and multiple service areas.
Key points
- The proposed maximum water impact fee was $3,764 per ¾-inch service unit, up from $1,161; the wastewater fee was $1,080, up from $418.
- The study identifies $36.55 million of water and $10.49 million of wastewater capital costs recoverable from growth over 10 years.
- Staff estimated maximum fees could generate $4.70 million annually, compared with $1.389 million in water and wastewater impact-fee revenue included in the FY2027 budget.
- Council voted 7-0 to postpone action until 8 December and seek stakeholder engagement and further analysis of alternatives.
Full report
Killeen City Council has delayed action on a proposed revision of water and wastewater impact fees that would more than triple the water charge for a standard residential-sized connection, after a unanimous council vote called for direct engagement with builders and developers.
The proposal would set maximum assessable charges of $3,764 for water and $1,080 for wastewater for a ¾-inch meter, compared with the current $1,161 and $418 respectively. The combined charge would therefore rise from $1,579 to $4,844 per service unit. Council voted 7-0 to postpone consideration until its 8 December meeting.
The fee update is intended to fund growth-related utility capacity projects identified in Killeen’s 2025 water and wastewater master plan. City staff and consultant Kimley-Horn said the programme is based on projected demand from 9,710 additional service units through 2035. The financial analysis calculated $36.55 million in water costs and $10.49 million in wastewater costs as recoverable through impact fees.
The water capital plan includes 13 projects, including the Chaparral pump station, Highway 195 ground storage tank, 24-inch Chaparral Road and Highway 195 transmission mains, a 20-inch Rodeo elevated storage tank transmission line, and distribution improvements in the upper and lower pressure planes.
Staff recommended adoption at the maximum rates, estimating annual impact-fee revenue of $3.65 million for water and $1.05 million for wastewater. That would be $3.31 million above the $1.389 million of combined impact-fee revenue assumed in Killeen’s FY2027 budget. Staff argued that impact fees allow growth-related expansion costs to be recovered from new development rather than through utility bills paid by existing customers.
However, several council members said the city had not sufficiently engaged stakeholders before bringing forward the measure. Councilmember David Bass said he was uncomfortable that staff had not met directly with builders and developers during the roughly year-long development of the proposal. He called for a stakeholder meeting and a compromise that affected parties could accept.
Councilmember Charles Kimble questioned whether a maximum-rate, single-service-area approach could undermine Killeen’s affordability. He asked staff to consider a tiered approach and multiple service areas. Developer Dylan Whitis, vice-chair of the Capital Improvements Advisory Committee, similarly asked the council to divide the system into service areas so projects are funded by developments receiving their benefit.
Staff said state law permits Killeen to use one water and wastewater service area because the systems operate as interconnected networks. It also said the fee for a development is assessed at final plat recordation and collected at building permit issuance; a later fee increase would not change the assessed fee for lots already covered by a recorded final plat unless development changes increase service units or meter size.
The city attorney advised that council must act within 30 days of the hearing. Staff will now hold a stakeholder meeting, examine issues raised by council, and return on 8 December. If substantive changes are required, the city may need to restart the statutory process.