Fort Worth opens data-centre moratorium process over water-supply concerns
City of Fort Worth Water Department, Texas · Meeting date: November 10, 2026 · Published: November 11, 2026
Fort Worth City Council held the first hearing on a proposed 90-day pause on new data-centre rezoning and permit applications, putting water demand and long-term supply availability at the centre of a regulatory review. Residents pressed the council for a longer and broader pause, while staff set out the state-mandated timetable for any moratorium.
Key points
- The proposed moratorium would apply to new data-centre rezoning and permit applications, while projects already vested in development would not be affected.
- Staff’s review would cover municipal water-supply impacts, long-term water availability, noise, land-use compatibility, building scale and mechanical infrastructure.
- Any moratorium requires a second public hearing, two ordinance readings and a three-fourths council vote; staff said a 90-day term could be extended once for a further 90 days.
- Public speakers repeatedly called for stronger rules, including wider setbacks, industrial zoning, studies of low-frequency noise and broader coverage of AI-related facilities.
Full report
Fort Worth has begun the formal process for a potential 90-day freeze on new data-centre development applications, with the city’s review expressly required to examine municipal water-supply impacts and long-term water availability.
The council held the first public hearing on November 10, following an August resolution directing the City Manager to initiate the moratorium process. The proposal would suspend the acceptance, processing and approval of new rezoning or permit applications for data centres. It would not affect projects that are already vested and in development, Assistant City Manager Jesica McEachern told the council.
During a moratorium, staff would undertake an expedited planning and regulatory review covering data-centre noise, water supply and long-term availability, land-use compatibility, building scale and mechanical infrastructure. The work is also intended to produce potential amendments to zoning ordinances, the city code and the water manual governing the facilities.
McEachern said state law prescribes a sequence of notices, two public hearings and two readings of a proposed ordinance before a moratorium can take effect. The council would need to approve the ordinance by a three-fourths vote. Under the timeline presented at the hearing, a moratorium adopted after the second reading could take effect on February 23 and run for 90 days, expiring May 24. The council could then consider one 90-day extension, the maximum period allowed under state law.
Public testimony strongly favoured the pause but argued that the city should use it to adopt more restrictive local controls. Several speakers raised concerns about water use, electricity demand, noise, generator emissions and the financial burden of infrastructure required for data-centre development. Conley Brewer asked whether the city had calculated the full infrastructure costs associated with proposed facilities and whether developers or existing residents would bear those costs.
Members of the city’s Data Center and Infrastructure Commission said its work had been compressed into roughly two months. Commissioner Ambika Sharma said the group had concentrated most heavily on land-use issues, but had not fully addressed whether facilities should be limited to heavy-industrial areas or require conditional-use permits. She also called for further independent research on noise and said she had supported a 600-foot setback, compared with the 350-foot figure discussed by the commission.
Other commissioners and residents called for setbacks of at least 500 feet, a study of low-frequency noise and requirements addressing decommissioning. Some speakers argued the moratorium should also cover semiconductor factories, testing facilities and other AI-related infrastructure.
The hearing was closed without a vote to impose the moratorium. The council’s next steps will determine whether Fort Worth moves from review to a temporary halt on new data-centre applications.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council Meeting, City of Fort Worth Water Department