DeSoto awards $3.42m contract for Westmoreland’s 10MG tank renewal
City of DeSoto Water and Wastewater Department, Texas · Meeting date: November 17, 2026 · Published: November 18, 2026
DeSoto City Council has selected O & J Coatings for rehabilitation of two 5MG treated-water storage tanks at the Westmoreland Pump Station. The award follows acceptance of Phase 1 works, which replaced the station’s eight high-service pumps and upgraded its electrical and distribution infrastructure.
Key points
- O & J Coatings won the tank-rehabilitation contract with a $3.42 million bid, the lowest of six submissions; council approved a total $3.762 million project budget including contingency.
- The contract covers sandblasting and recoating two 5MG treated-water storage tanks, plus replacement of corroded ladders, steel floor and roof plates, beams, roof supports and rafters.
- Council also approved an $80,500 Garver amendment for up to 100 specialist tank-coating inspection visits, increasing the professional-services budget to $2.032 million.
- The city accepted Phase 1 of the Westmoreland rehabilitation at a final construction cost of $9.562 million, $562,453 below its approved construction budget.
Full report
DeSoto City Council has awarded O & J Coatings Inc a $3.42 million contract to rehabilitate two 5-million-gallon treated-water storage tanks at the Westmoreland Pump Station, advancing the second stage of a wider renewal programme at one of the city’s priority water-distribution assets.
The council approved a total project budget of $3.762 million, including contingency, for the tank works. O & J Coatings, based in Hurst, Texas, submitted the lowest of six competitive bids received on 29 October. Its bid was $75,000, or 2.2%, below the second-lowest submission from Viking Industrial Painting.
The work comprises sandblasting and recoating both ground storage tanks, which together provide 10MG of treated-water storage. It also includes replacement of corroded interior access ladders, steel floor and roof plates, and structural steel beams, roof supports and rafters. The bid items also cover tank isolation and draining, sediment removal, surface preparation, disinfection, and removal and reattachment of chloramination and electrical equipment.
Construction is scheduled to begin in January 2027 and take 12-14 months. The project is funded through the Public Utilities Water & Sewer Capital Improvements Fund and future bond-sale proceeds.
Council separately approved an $80,500 amendment to Garver’s professional-services agreement to provide specialist inspection during tank recoating. The scope allows up to 50 visits for each tank, or 100 visits in total, to inspect interior and exterior surface preparation and coating application. The amendment raises the Westmoreland pump station project’s professional-services budget from $1.951 million to $2.032 million.
The added inspection scope results from DeSoto’s decision to split the pump-station and tank-rehabilitation elements into separate phases after the original combined procurement drew bids significantly above the project budget. The tank inspection work will be undertaken by a certified protective-coatings specialist, with each visit priced at $770, including Garver’s fixed fee.
The tank award follows council acceptance of Phase 1 at Westmoreland, completed by CLW Water Group. Phase 1 construction began in March 2025 and reached substantial completion in June 2026. Its final cost was $9.562 million, against a construction budget of $10.124 million.
Phase 1 replaced all eight pumps, motors and piping at the station, added crossover piping between the 860 and 798 pressure zones, installed water-meter vaults and balancing valves for flows from Dallas Water Utilities, and introduced dual-feed electrical redundancy. The city also upgraded lighting, security, fencing, coatings and the station roof, while adding a canopy to protect outdoor pumps. The Westmoreland programme was identified as a priority project in DeSoto’s 2021 Water Distribution System Master Plan.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council Meeting, City of DeSoto Water and Wastewater Department