Bartlett advances Fletcher Creek sewer tank with $5.68m pipe buy
City of Bartlett Water Wastewater Services, Tennessee · Meeting date: November 10, 2026 · Published: November 11, 2026
Bartlett’s Board of Mayor and Aldermen has approved the advance purchase of pipe for a 3.0-million-gallon sewer equalization tank intended to manage Fletcher Creek Basin flows to Memphis and provide capacity beyond current needs. The city expects early procurement to enable spring and summer 2027 construction rather than waiting for contractor-led material delivery.
Key points
- The board unanimously approved a maximum $5,683,893.34 purchase from ISCO Industries for 132-inch Weholite HDPE pipe for 3.0 million gallons of equalization storage.
- The tank will provide 1.5 million gallons required for existing Fletcher Creek system needs and a further 1.5 million gallons for anticipated development.
- Staff said procuring pipe ahead of construction could save more than $1 million through avoided contractor mark-up and tax, while allowing work to begin in the dry construction season.
- The city also approved a $200,000 SRF loan-administration agreement with Community Development Partners, with authorised additional services up to $50,000.
Full report
Bartlett has taken a major procurement step towards restoring and expanding sewer capacity in its Fletcher Creek Basin, approving up to $5.68 million for 132-inch HDPE pipe for a proposed 3.0-million-gallon equalization tank.
The Board of Mayor and Aldermen unanimously approved the contract with ISCO Industries for the manufacture and delivery of Weholite pipe, including a 2.0-million-gallon base bid and two 0.5-million-gallon alternates. The maximum value is $5,683,893.34, while the minimum value stated in the procurement documents is $5,467,093.34.
The pipe will form eight parallel underground barrels, each approximately 520ft long, on city-owned land east of Bartlett’s fleet-services site. The facility is intended to buffer peak flows sent south to Memphis wastewater treatment plants from the Fletcher Creek Basin.
Engineering director John Horne said Memphis requested three equalization tanks in 2019 to better control flows delivered from Bartlett. Two tanks at the Union Depot development, providing 600,000 gallons of storage, are already operational. Bartlett’s subsequent analysis concluded that the third tank required 1.5 million gallons for existing system needs, but the city has opted for 3.0 million gallons to accommodate anticipated development.
City officials said the lack of equalization storage had prevented further sewer connections in the area. The additional 1.5 million gallons of planned capacity is intended to support future development in the Fletcher Creek Basin, including land in Bartlett’s industrial area.
Rather than have the eventual construction contractor procure the material, Bartlett will buy and store the pipe itself at Wastewater Treatment Plant No. 1. Horne said the approach would avoid at least a 15% contractor mark-up, save tax and produce savings of more than $1 million. More importantly, he said, it would allow pipe deliveries to begin on 11 January 2027 and enable excavation during the drier spring and summer months. Staff projected a February construction bid, a March award and construction beginning between April and June, with a 12- to 18-month build period.
The city selected the product through a sole-source process, stating that InfraPipe was the only manufacturer identified with sustained experience producing 132-inch ASTM F894 HDPE pipe. ISCO Industries is the distributor, while manufacturing will take place in Jacksonville, Florida.
The board also approved professional services from Community Development Partners to administer the project’s Tennessee State Revolving Fund loan. The agreement carries a $200,000 lump-sum fee, with further authorised work capped at $50,000, and is contingent on the city receiving SRF funding. Finance staff said the city was in phase two of the SRF process for an estimated $21.4 million loan, with an interest rate below 1% required under the programme.