OJRSA regional sewer plan hinges on $65m ‘affordable’ capital programme
Oconee Joint Regional Sewer Authority, South Carolina · Meeting date: November 12, 2026 · Published: November 17, 2026
A preliminary Raftelis study found that absorbing municipal collection systems into a regional OJRSA structure could save about $400,000 a year in operations, but the saving is overwhelmed by system-wide rehabilitation needs. Consultants said a constrained capital programme offers the most manageable path, while full funding scenarios would drive far steeper customer bills.
Key points
- Raftelis modelled an approximately $65 million five-year affordable CIP for a combined OJRSA and municipal collection system, funded through a mix of cash and debt.
- The combined system was estimated to reduce collection-system operating costs from about $2.64 million to about $2.2 million annually, a saving of roughly $400,000.
- OJRSA’s 20-year CIP totals approximately $314 million-$315 million before inflation; priority 1 and 2 projects alone were estimated at about $15 million per year.
- The study estimated that full collection-system replacement needs could reach about $6.67 million per year, making full capital funding unaffordable under the model.
- The committee asked Raftelis to finalise its report by year-end and planned a January 7 presentation to elected officials; First Tryon will begin system-valuation work.
Full report
Oconee Joint Regional Sewer Authority’s proposed regional sewer system will require a deliberately constrained capital programme if it is to avoid the most severe rate impacts identified in a preliminary financial study.
Raftelis, which is assessing the feasibility of bringing the area’s municipal collection systems under the OJRSA umbrella, presented an approximately $65 million five-year affordable capital improvement programme as the most manageable of the scenarios modelled. The programme would allow the combined authority to decide how funding is divided between OJRSA treatment and transmission assets and municipal collection systems.
The study’s central conclusion was that consolidation is not a straightforward rate-saving proposition. While Raftelis estimated that a combined operation could reduce collection-system operating costs from approximately $2.64 million to $2.2 million annually, producing about $400,000 of annual savings, those efficiencies are small relative to the capital burden facing the systems.
OJRSA’s existing 20-year CIP totals approximately $314 million-$315 million, excluding inflation and including some growth-related projects that may not proceed. Priority 1 and 2 projects alone were estimated at roughly $15 million annually. The consultants also said city collection-system needs are uncertain: a 2023 regionalization study identified about $2 million per year, updated information supplied for the rate study indicated about $3 million, and a high-level replacement-cost analysis pointed to potential needs of about $6 million-$7 million annually.
Under a full combined-system capital scenario, Raftelis said the impact on bills was unacceptable. Using a 5,000-gallon monthly residential customer as its benchmark, the presentation showed a standardised combined-system bill of $128 in 2028 in the full-CIP model. The affordable scenario instead began with a $71 monthly bill for a Seneca customer in 2028, followed by annual increases.
The status quo was not presented as cost-free. Raftelis assumed that OJRSA would gain borrowing capacity even in that case, since its current inability to borrow would otherwise require operating revenues to rise from about $7 million to more than $20 million to cash-fund the level of capital work under consideration. The consultants modelled roughly $27.5 million of borrowing for projects spanning 2026-28 and a further $36 million for 2029-30 under the status-quo debt plan.
Committee members emphasised that infrastructure costs will persist whether or not regionalization proceeds. They also noted that OJRSA and two of the municipalities face consent-order-related work. Raftelis said regionalization could provide a larger revenue base, greater borrowing capacity and potentially stronger access to state loans and grants, but said the financial case could not stand on operating efficiencies alone.
Several unresolved choices could add to customer costs. A 10% municipal franchise fee, not included in the analysis, would increase the illustrative $71 bill to $77, Raftelis said. Purchasing municipal collection systems rather than transferring them with existing debt would also raise bills. The study assumed cities would remain the most cost-efficient billing providers and would be reimbursed for that work.
The committee asked Raftelis to give equal weight to the full-CIP, reduced-CIP and affordable-CIP cases in its final report, while making clear why the affordable programme is the preferred direction. The final report is expected by year-end for presentation to elected officials on January 7. First Tryon will also begin work on valuing the collection systems, while OJRSA staff reassess the priority and timing of the existing CIP.
This summary was generated by AI based on the source document and may contain errors.
Source: Reconstitution Committee Meeting, Oconee Joint Regional Sewer Authority