Laval advances C$5.85m aqueduct pressure-regulation programme
Laval, Quebec · Meeting date: November 11, 2026 · Published: November 16, 2026
Laval’s executive committee has recommended Eurovia Québec Grands Projets for a 730-day programme to install underground pressure-regulation chambers on the city’s aqueduct network. The committee also recommended associated engineering and laboratory services and earmarked C$7.19 million in project funding, conditional on municipal council awarding the works contract.
Key points
- Eurovia Québec Grands Projets was recommended for contract DOS-3686, valued at C$5,850,000.01, for a 730-day term.
- CIMA+ was recommended for C$1,092,810.93 of construction supervision and C$58,464.79 of technical assistance.
- Solmatech was recommended for C$119,871.22 of materials placement and field and laboratory testing.
- The committee recommended financing C$7,187,600, net taxes included, from bylaw L-13249-F, subject to council approval of the main contract.
Full report
Laval has moved to procure a C$5.85 million package of works to install underground pressure-regulation chambers on its aqueduct network, with the executive committee unanimously recommending the award to Eurovia Québec Grands Projets.
The recommended contract, DOS-3686, has a 730-day term and covers implementation of the chambers. The works are associated with the Saint-Vincent-de-Paul, Pont-Viau, Marigot, Souvenir-Labelle and L’Abord-à-Plouffe districts.
The executive committee also unanimously recommended the supporting professional-service mandates required for delivery. CIMA+ would provide construction supervision for C$1,092,810.93 under contract DOS-1829, lot 4, and technical assistance for C$58,464.79 under contract SP-30143, lot 1. Solmatech would undertake materials placement and field and laboratory testing for C$119,871.22 under contract DOS-2786, lot 1.
In addition, the committee authorised an estimated C$34,590 payment covering fees under Quebec’s regulation on traceability of excavated contaminated soils, through the government’s Traces Québec system, as well as the levy supporting treatment and recovery of excavated contaminated soils. That authorisation is conditional on municipal council awarding the main works contract.
The committee further recommended that C$7,187,600, net taxes included, be financed from funds available under bylaw L-13249-F, also conditional on council’s award of DOS-3686.
The resolutions allow work to begin after Eurovia provides the guarantees required under the tender documents, subject to the council decision. Separately, the committee unanimously approved a collaboration agreement with the Université du Québec à Montréal for drilling, developing and monitoring two groundwater observation wells at Bois de l’Équerre and Bois Papineau.