Cincinnati secures Terrace Park water switch through 2066
Greater Cincinnati water works, Ohio · Meeting date: November 18, 2026 · Published: November 19, 2026
Cincinnati City Council has authorised Greater Cincinnati Water Works to take over retail water service in Terrace Park from Indian Hill, under an emergency agreement running to December 31, 2066. The transition is expected to start service in 2028, with a Little Miami River crossing planned to complete the village’s fire-flow supply.
Key points
- Council approved the Terrace Park retail surplus-water agreement as an emergency measure, with every recorded vote in favour.
- GCWW is estimated to begin retail service on January 1, 2028, following completion of the Wooster connection and Terrace Park’s termination of its Indian Hill agreement.
- A second connection, the Little Miami Crossing, is anticipated by the date three years after Terrace Park gives notice to Indian Hill and is intended to provide adequate fire flow.
- Terrace Park’s existing water-system infrastructure will transfer to Cincinnati on the go-live date; GCWW will become the exclusive domestic-water supplier after the Little Miami Crossing enters service.
- If Terrace Park exits before the transition ends, it must reimburse documented GCWW transition costs, capped at $10 million.
Full report
Cincinnati City Council has approved a 40-year retail water service agreement under which Greater Cincinnati Water Works (GCWW) will replace Indian Hill as Terrace Park’s water provider.
The emergency ordinance, passed on November 18, authorises the City Manager to execute the agreement through December 31, 2066. The move gives GCWW responsibility for retail distribution, metering, billing and collections for properties within Terrace Park’s corporate limits once the transition is complete.
The agreement sets out a two-stage infrastructure programme to shift the village’s supply. GCWW will build a Wooster connection to allow the initial transfer of retail service from Indian Hill. The estimated go-live date is January 1, 2028, approximately one year after Terrace Park gives notice terminating its current Indian Hill service agreement.
Terrace Park will retain standby arrangements with Indian Hill for fire-flow requirements during the interim period. GCWW will then construct a second connection, the Little Miami Crossing. Once the crossing is complete and in service, the two connections are intended to provide retail service sufficient to meet Terrace Park’s fire-flow needs. The agreement anticipates completion by the date three years after Terrace Park’s notice to Indian Hill.
At the go-live date, Terrace Park’s water storage, distribution and related service-area infrastructure will transfer to Cincinnati and become part of the Cincinnati Water System. Fire hydrants are excluded from the transferred service-area infrastructure. GCWW will have the right to use existing easements and rights-of-way in Terrace Park for construction, operation, maintenance, repair and replacement of water facilities.
After the Little Miami Crossing begins operating, Cincinnati will become the sole supplier of domestic water to Terrace Park properties. The agreement also gives Cincinnati a right of first refusal to serve properties added to Terrace Park through merger, annexation or other means.
The supply will be provided as surplus treated water, meaning it remains dependent on water being available beyond the needs of Cincinnati users. In supply constraints or emergencies, Cincinnati may allocate and prioritise service among non-Cincinnati jurisdictions on a reasonable basis, with no preference based on an earlier contract date.
Terrace Park will be subject to GCWW requirements and Cincinnati retains sole discretion over system operations, capital improvements, rate-setting, billing and collections. Initial monthly fire-hydrant maintenance charges will range from $2.50 for meters from five-eighths of an inch to 1.5 inches, to $4 for meters greater than eight inches.
The agreement also protects GCWW’s transition expenditure. Should Terrace Park terminate before the transition period ends, it must reimburse actual, reasonable and documented costs incurred by GCWW, subject to an aggregate cap of $10 million.
This summary was generated by AI based on the source document and may contain errors.
Source: Cincinnati City Council, Greater Cincinnati water works