Capacity mismatch in Cleveland relief sewer project triggers residential backups
Cleveland Water Department, Ohio · Meeting date: April 6, 2026 · Published: April 7, 2026
Residents are demanding operational interventions after a new 48-inch sanitary relief sewer overwhelmed downstream legacy pipes, as City Council simultaneously introduces a new county-wide sewer repair agreement to address ongoing stormwater challenges.
Key points
- The Joanne Drive sanitary relief sewer project installed a 48-inch pipe that feeds into 8-inch lines, creating a severe bottleneck.
- During heavy rain events, combined stormwater and sewage is backing up into basements instead of being diverted through combined sewer overflows.
- City Council introduced Ordinance 455-2026 to establish a two-year, as-needed storm and sanitary sewer repair agreement with Cuyahoga County.
- Council also advanced property easements to the Northeast Ohio Regional Sewer District (NEORSD) for the Mill Creek Restoration Project.
Full report
Cleveland's wastewater infrastructure is under heightened scrutiny following reports that a recent sanitary relief sewer project has inadvertently caused severe combined sewer backups into residential basements due to an extreme capacity mismatch.
During an April 6 City Council meeting, residents detailed the ongoing fallout from the Joanne Drive sanitary relief sewer project. The city installed a 48-inch diameter sanitary relief sewer uphill from Invermere Avenue. However, the downstream infrastructure was not upgraded to match; the 48-inch pipe feeds directly into legacy 8-inch pipes on Invermere Avenue, which then connect to a perpendicular 8-inch main on Lee Road.
When the system becomes overwhelmed during heavy heavy rain, the bottleneck forces combined stormwater and sanitary sewage into residential basements. Residents testified that the local sewer department has the ability to open combined sewer overflows to divert the contaminated water into local water bodies, arguing that the backups are the result of conscious operational decisions rather than random weather events. The infrastructure challenges are not isolated to one neighborhood, with Councilman Brian Casey noting that recent storms caused severe, impassable flooding on West 130th and West 150th streets.
Simultaneously, the City Council took procedural steps to address broader regional water and wastewater infrastructure needs. Council introduced Ordinance 455-2026, an emergency measure authorizing the Director of Public Utilities to enter into a Utilities Repair Agreement with Cuyahoga County. The agreement will allow the city to pay or reimburse the county for directly related costs incurred repairing storm and sanitary sewer lines on an as-needed basis. The contract covers a two-year period, with an option to renew for an additional year.
Additionally, the council introduced Ordinance 453-2026, which grants easement rights to the Northeast Ohio Regional Sewer District (NEORSD) for several city-owned properties located along the Mill Creek corridor through the Kerruish Basin. The easements will facilitate NEORSD's ongoing Mill Creek Restoration Project. Both ordinances were referred for administrative and committee review.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council, Cleveland Water Department