Union County wastewater commitments near permit limits at Crooked Creek
Union County Public Works, North Carolina · Meeting date: November 16, 2026 · Published: November 17, 2026
Union County commissioners approved the November wastewater-capacity update as Crooked Creek WRF reached 95.2% of permitted capacity on an actual-plus-obligated-flow basis. Twelve Mile Creek WRF was at 91.0%, with development requests continuing in both service areas.
Key points
- Crooked Creek WRF has 1.9 mgd of permitted capacity, 1.256 mgd of average daily flow and 1.809 mgd of actual plus permitted obligated flows.
- Twelve Mile Creek WRF has 7.5 mgd of permitted capacity, 5.128 mgd of average daily flow and 6.826 mgd of actual plus permitted obligated flows.
- Development backlogs total 23 projects seeking 0.493 mgd at Crooked Creek and 33 projects seeking 0.611 mgd at Twelve Mile Creek.
- Commissioners approved the monthly wastewater treatment capacity update on November 16.
Full report
Union County’s Crooked Creek Water Reclamation Facility is 95.2% committed against its permitted treatment capacity once current flows and permitted obligations are counted, according to the monthly wastewater-capacity update approved by the Board of Commissioners on November 16.
Crooked Creek has permitted capacity of 1.9 million gallons per day (mgd). Its 12-month rolling average daily flow was 1.256 mgd, or 66.1% of capacity, while actual flow plus permitted obligated flows totalled 1.809 mgd.
The county’s larger Twelve Mile Creek WRF reported 7.5 mgd of permitted capacity and a 5.128 mgd average daily flow, equivalent to 68.4% of capacity. Its actual-plus-obligated-flow figure was 6.826 mgd, or 91.0% of permitted capacity.
Both facilities also have development proposals in their review pipelines. At Crooked Creek, 23 projects were seeking a combined 0.493 mgd: three approved projects awaiting permit submittal sought 0.066 mgd; nine projects in engineering-plan review sought 0.224 mgd; and 11 sketch-plan-review projects sought 0.206 mgd.
At Twelve Mile Creek, 33 projects represented 0.611 mgd of requested flow. Five approved projects pending permit submittal accounted for 0.037 mgd, 13 engineering-plan-review projects sought 0.290 mgd, and 15 sketch-plan-review projects sought 0.284 mgd.
The update also reported 2.5 inches of rainfall at Twelve Mile Creek and 3.1 inches at Crooked Creek. Other county facilities remained materially less committed: Olde Sycamore was at 26.7% of permitted capacity on an actual-plus-obligated-flow basis, Tallwood at 34.0%, and Grassy Branch at 30.0%.
This summary was generated by AI based on the source document and may contain errors.
Source: Board of Commissioners, Union County Public Works