OWASA weighs expansion of in-house water-main crews after $1.5m-a-year savings estimate
Orange Water and Sewer Authority, North Carolina · Meeting date: November 12, 2026 · Published: November 16, 2026
Orange Water and Sewer Authority’s board has backed a FY2028-budget evaluation of expanding its internal construction crew for water-main renewals. The move follows preliminary analysis showing an internal cost of about $205 per linear foot, against $504 per foot for comparable contractor work.
Key points
- OWASA replaced an average 1.87 miles of water main annually in FY2024-FY2026, short of its 2.5-mile annual goal.
- The internal crew completed 4.0 miles over the three-year period, compared with 1.6 miles by contractors.
- Staff estimated preliminary savings of about $1.5 million annually from internal delivery, but cautioned that contractor projects are generally larger and more complex.
- The evaluation will assess staffing, equipment, facilities, project pipeline, legal limits and whether internal work can raise renewal rates or displace contractor work.
Full report
Orange Water and Sewer Authority will assess an expansion of its in-house water-main construction capacity as it seeks to close a persistent gap against its renewal target and test whether the utility can capture further savings from self-delivered projects.
The Board of Directors approved staff’s request to undertake a comprehensive evaluation as part of FY2028 budget development. The decision does not authorise new staff or resources, but launches an assessment of the costs, operational requirements and potential benefits of enlarging the Internal Construction Crew Water Main Replacement Program.
OWASA operates more than 390 miles of water main across its 35-square-mile service area. It has set a replacement goal of 2.5 miles annually, based on a 2020 distribution-system management study that considered break history, deterioration and renewal needs. Actual replacement averaged 1.87 miles a year across FY2024, FY2025 and FY2026—an annual shortfall of 0.63 miles.
The internal seven-person crew has been the principal delivery vehicle for smaller, less complex schemes, generally involving pipe of 8 inches or less. It completed 4.0 miles of replacement work in the past three years, or about 71% of the total, while contractors delivered 1.6 miles.
Staff’s preliminary comparison of eight internally delivered projects with two comparable contractor projects found an average internal cost of approximately $205 per linear foot, compared with $504 per linear foot for contractor work. Staff estimated that this differential equated to roughly $1.5 million in annual savings over the three-year period.
However, OWASA stressed that the comparison is not definitive. Contractor-delivered schemes tend to be larger and more difficult, potentially carrying added traffic control, restoration, construction coordination and project-management costs. The contractor benchmark also drew on only two projects.
The forthcoming review will identify additional projects suited to internal delivery; establish the staffing, supervision, equipment, facilities, materials, training and engineering support required; and compare costs and benefits after accounting for differing project complexity. It will also consider operational factors including emergency response, workforce knowledge, flexibility and system reliability.
State law constrains the work OWASA can perform with its own resources: an internal project must have a total cost of $500,000 or less, or labour costs of $200,000 or less. Larger or more complex schemes will therefore generally remain contractor-delivered.
The utility said it will also examine whether the internal model could have applications beyond water-main replacement, including sewer rehabilitation work now undertaken by contractors.
This summary was generated by AI based on the source document and may contain errors.