Hoke County lifts PWC water ceiling as Rockfish Creek supply study begins
Hoke CO Regional Water System, North Carolina · Meeting date: November 16, 2026 · Published: November 17, 2026
Hoke County commissioners approved a 10-year PWC water-services agreement raising the county's monthly limit from 51 million to 57 million gallons. They also authorised an MOU with Robeson County to assess whether Rockfish Creek can support a regional supply project.
Key points
- The PWC agreement raises Hoke County's monthly water limit by 6 million gallons, from 51 million to 57 million gallons, in 3 million-gallon increments.
- Either party may terminate the 10-year PWC agreement with 24 months' notice.
- Commissioners cautioned that approaching the 57 million-gallon ceiling could require upgrades to Hoke County pumps and metering infrastructure.
- The Rockfish Creek MOU commits Hoke and Robeson counties only to initial work assessing water availability and connection to the system; it does not settle ownership, costs or funding.
Full report
Hoke County has taken parallel steps to increase the resilience of its water supply, approving a 10-year agreement with PWC that raises its monthly water allocation while authorising initial feasibility work on a potential regional source at Rockfish Creek.
The PWC Intergovernmental Water Services Agreement raises Hoke County's monthly water limit to 57 million gallons, from 51 million gallons currently, with the increase structured in 3 million-gallon increments. Either party can end the agreement by giving 24 months' notice.
Commissioners said the additional contractual allocation should not be treated as immediately available capacity for further connections. County usage was put at about 42 million gallons per month during the discussion. The county's existing pumping equipment has operating limits, and commissioners said that moving substantially closer to the 57 million-gallon threshold could require work on county-side pumps and the metering system.
The county attorney said the present infrastructure is adequate for current conditions, but that higher volumes would require additional infrastructure. A commissioner urged the county to incorporate potential upgrades into upcoming utility budgets, noting that the utility operates as an enterprise supported by its own revenues.
Alongside the PWC agreement, the board approved a memorandum of understanding with Robeson County for the Rockfish Creek Regional Water Supply Project. The agreement sets out the counties' respective commitments for initial work to determine whether water can be obtained from Rockfish Creek and connected into the system.
The MOU does not commit either county beyond that initial assessment. It does not address project ownership, capital costs or funding arrangements.
Commissioners characterised the Rockfish proposal as a regional response to supply issues affecting both counties, including Hoke County and the northern part of Robeson County. One commissioner said a project of that scale could be beyond the reach of either utility alone, but that a joint undertaking could improve its ability to secure state approval and financing.
The board also discussed the possibility that Rockfish Creek could provide a separate county-controlled source if the feasibility and permitting work supports the project. A commissioner said the PWC agreement provides a 10-year planning horizon while the county explores the regional partnership, alongside its existing wells in the western part of the county.
The two approvals place Hoke County on a dual-track supply strategy: a larger contracted volume from PWC in the near term, coupled with early-stage investigation of a jointly developed regional source. Commissioners said county growth projections had been considered in the PWC arrangement and that the county believed it had sufficient supply planning for the next 10 years.
This summary was generated by AI based on the source document and may contain errors.
Source: Hoke County Board of Commissioners November 16, 2026 regular meeting - Nov 16, 2026, Hoke CO Regional Water System