Harnett approves $1.57m design push for Coats and Buies Creek sewer expansion
Harnett County Department of Public Utilities, North Carolina · Meeting date: November 16, 2026 · Published: November 17, 2026
The Harnett County Board of Commissioners has authorised a $1.569 million amendment with Highfill Infrastructure Engineering for the second phase of sewer upgrades in the Buies Creek and Coats corridors. The design work is being accelerated to meet a January 2027 state funding submission requirement.
Key points
- The amendment with Highfill Infrastructure Engineering covers Phase 2 design, permitting, field investigations, easement support and bidding services, with total compensation capped at $1.569 million.
- Phase 2 includes about 10,000ft of 24- to 30-inch gravity sewer, intended to increase capacity upstream of SLS-10B and eliminate lift stations 7 and 11.
- The project also calls for a replacement SLS-4 pump station in Coats, initially rated at 810gpm and designed for eventual peak flows of 1,920gpm, plus 9,500ft of 12-inch force main.
- The county estimates Phase 2 at about $15 million and has made it its top funding request; $10.6 million in legislative funding is expected to cover Phase 1.
Full report
Harnett County has approved a $1.569 million engineering amendment for Phase 2 of the Coats and Buies Creek Sewer Improvements, moving forward with a capacity programme for wastewater infrastructure that staff said is approaching, or has reached, its limits in the county’s central and northeast areas.
The amendment to Harnett Regional Water’s contract with Highfill Infrastructure Engineering covers preliminary and final design, environmental and utility investigations, permitting, easement-acquisition assistance and bid-phase services. The work is being expedited to meet Drinking Water/Wastewater State Reserve requirements for a design-and-bid submission by 8 January 2027, unless an extension is granted.
Phase 2 targets the network upstream of Sewer Lift Station 10B. It will design approximately 10,000ft of 24- to 30-inch sanitary sewer running from SLS-10B toward US 421 and along East Buies Creek to Leslie Campbell Avenue. The stated objectives are to provide capacity for projected 30-year flows and take lift stations 7 and 11 out of service.
The programme also includes replacement of the SLS-4 Coats pump station. The new station is planned initially for 810 gallons per minute, with permanent structures sized for peak flows of 1,920gpm. It would be built on a larger, more accessible site on higher ground, addressing flooding and maintenance-access concerns at the existing installation. Roughly 9,500ft of 12-inch force main would connect the new station along Fleming Road and McLamb Road to NC 27, where it would join the existing SLS-4 force main.
The approved $1.569 million cap comprises $879,000 in lump-sum basic services and up to $690,000 in time-and-materials services. Highfill’s scope includes route assessment, wetland and stream delineation, geotechnical work, utility investigations and applications for state sewer-extension, erosion-control and road-encroachment approvals.
Harnett Regional Water’s director told commissioners that the overall programme is divided into two phases. Phase 1 will run from Lillington to Keith Hills and is expected to be covered by $10.6 million in legislative funding received about three years ago. Phase 2, from Keith Hills to SLS-4, is estimated at about $15 million. The county has submitted a funding request for that phase and identified it as its highest priority.
The contract amendment advances design rather than construction, but it positions the utility to seek bids after design and permitting are complete.