Cumberland County pushes Gray’s Creek PFAS water work into 2027
Cumberland County, North Carolina · Meeting date: November 12, 2026 · Published: November 16, 2026
The Board of Commissioners approved a 123-day extension to the US$5.93 million Gray’s Creek Phase 1 distribution contract, delaying completion to April 2027. It also extended the associated test-well programme through December 2027 without increasing its US$775,996 contract ceiling.
Key points
- Jymco Construction’s US$5.93 million water-distribution contract now has a substantial-completion date of March 24, 2027 and final-completion date of April 23, 2027.
- The distribution work will provide potable-water infrastructure to properties dependent on private wells contaminated by Fayetteville Works PFAS.
- The contractor cited Build America, Buy America documentation, material approvals and lead times, service sequencing, and water-source and testing coordination as schedule constraints.
- Bill’s Well Drilling’s Phase 1 test-well contract was extended at zero cost through December 31, 2027, allowing time for one additional well at a location still to be identified.
Full report
Cumberland County has reset the delivery schedule for key parts of its Gray’s Creek PFAS water programme after approving no-cost extensions that move both distribution construction and source-water investigation into 2027.
The Board of Commissioners approved Change Order No. 1 for the US$5.927 million Gray’s Creek Phase 1 Water Distribution Packages 1 and 2 contract with Jymco Construction Company. The change order extends substantial completion by 123 calendar days, from November 21, 2026 to March 24, 2027, and final completion from December 21, 2026 to April 23, 2027. It also removes the original November 2, 2026 Milestone 1 deadline.
The contract value remains unchanged. Awarded in April and started under a July 9 notice to proceed, the project includes water mains, valves, hydrants, service connections and associated infrastructure for properties currently reliant on private wells contaminated by Fayetteville Works PFAS.
Jymco attributed the delay to material approvals, Build America, Buy America compliance documentation, resubmittals and procurement lead times. The contractor also cited coordination of residential meter locations, unavailable 1-inch service materials, and water-source, flushing and testing requirements. As of November 3, it reported 17% of Package 1 water main installed and 3.8% of Package 2.
Commissioners also approved a revised second change order for the Gray’s Creek Phase I Test Well Program contract with Bill’s Well Drilling Co. The zero-cost amendment keeps the contract’s not-to-exceed amount at US$775,996 while extending substantial completion by 778 days to October 2, 2027 and final completion by 868 days to December 31, 2027.
The amendment covers work completed to date and retains the contractor for an additional test well, whose location has not been identified. The test-well programme had originally covered three wells, before a 2025 change order expanded investigation of deeper wells at Gray’s Creek and Alderman Road elementary schools.
County utilities staff said source-water development and Phase 2 planning remain under way. The county is also completing two large test wells and pilot treatment and testing, work intended to provide additional system capacity and redundancy.