Durham adds $941k to PFAS adviser contract for 2029 compliance drive
City of Durham Department of Water Management, North Carolina · Meeting date: November 16, 2026 · Published: November 17, 2026
The City Council approved the second amendment to HDR Engineering’s PFAS consulting contract as Durham develops powdered activated carbon treatment at Brown Water Treatment Plant. The wider project, which has an estimated lifecycle cost of $32 million, has also absorbed electrical and liquid-ammonia storage upgrades at Brown and Williams water treatment plants.
Key points
- Council approved a $940,912 amendment for HDR Engineering, lifting its PFAS consulting-support contract to $3,043,677.
- The amendment raises available contract contingency to $265,118 and authorises amendments up to a total contract cost of $3,308,795.
- HDR will administer the design-build contract and provide design review, cost review, construction support and startup support.
- Durham selected powdered activated carbon following a treatment study completed in September 2025, with the system intended to remove PFAS from the city water supply.
- The programme is intended to support compliance with EPA PFAS drinking-water regulations by April 2029.
Full report
Durham City Council has authorised a $940,912 expansion of HDR Engineering, Inc. of the Carolinas’ owner-advisor role on the city’s PFAS treatment programme, bringing the engineering consultant’s contract to $3.04 million.
The amendment supports the design-build delivery of a full-scale powdered activated carbon (PAC) treatment system at Brown Water Treatment Plant, selected by Durham following a treatment alternatives study completed in September 2025. The city said PAC offered the best balance of PFAS removal performance and cost-effectiveness across its tested sources.
The programme is intended to ensure that the utility meets the US Environmental Protection Agency’s PFAS drinking-water requirements by April 2029. Durham has tested raw-water sources and treated water from its Brown and Williams treatment plants since February 2018. It said PFAS levels are lower than in several surrounding areas, but action is still required to comply with the federal limits.
HDR’s original January 2024 contract was valued at $392,495 for the treatment study. A first amendment, worth $1.71 million, added owner-advisor services for procuring a design-build team and supporting design and construction of the Brown PFAS upgrades. The latest amendment takes the total consulting contract value to $3,043,677.
The new scope includes $197,416 for project and design-build contract administration; $52,464 for guaranteed-maximum-price review, negotiations and cost-estimating review; $176,019 for 30% and 60% design reviews, quality assurance and value engineering; and $415,013 for final design review and construction support. It also includes $50,000 each for additional as-needed adviser services and startup support.
Durham has added $94,091 in contingency to the amendment and retained $171,027 of unused original-contract contingency, creating a total contingency of $265,118. The council also authorised further amendments provided the cumulative original contract and amendments do not exceed $3,308,795.
The design-build scope has expanded beyond PFAS treatment. It now includes replacement of electrical-distribution equipment nearing the end of its useful life at both Brown and Williams plants, along with replacement of liquid ammonia storage tanks that the city said have suffered damage and degradation. HDR will provide design and construction management support for those additions as part of the same programme.
Durham estimates the total lifecycle cost of the PFAS project at $32 million.
This summary was generated by AI based on the source document and may contain errors.
Source: November 16, 2026 City Council Meeting, City of Durham Department of Water Management