Durham eyes $7.2m design ceiling for South Durham reclamation plant upgrade
City of Durham Department of Water Management, North Carolina · Meeting date: October 8, 2026 · Published: October 9, 2026
Durham’s October 8 work-session agenda includes a $5.16 million amendment for final design, permitting and bidding services at the South Durham Water Reclamation Facility. The proposed amendment would substantially expand McKim & Creed’s existing contract for tertiary-filter replacement and other process rehabilitation work.
Key points
- The proposed Amendment No. 1 would add $5,162,857 to McKim & Creed’s Contract No. 21869.
- The revised professional-services contract value would be $6,688,857.
- Durham proposes adding $363,686 in contingency, bringing total contingency to $516,286, including $152,600 of unused original contingency.
- The requested authority would set a total contract-and-contingency ceiling of $7,205,143.
Full report
Durham City Council has placed a proposed $5.16 million design amendment for the South Durham Water Reclamation Facility on its October 8 work-session agenda, positioning the city to advance tertiary-filter replacement and miscellaneous process rehabilitation work at the wastewater plant.
The proposed Amendment No. 1 to Contract No. 21869 with McKim & Creed would cover final design, permitting and bidding services for the project. If authorized, it would raise the consultant’s contract from its original level to a revised total of $6,688,857.
The agenda also calls for $363,686 of additional contingency funding. Together with $152,600 in unused original contingency, this would bring the contingency allocation to $516,286. The requested authorization would allow the City Manager to negotiate and execute further amendments, provided the original contract and all amendments do not exceed $7,205,143, including contingency.
The reclamation-facility item was listed among the Water Management Department’s consent-calendar business and was not pulled for discussion in the available meeting transcript. It remained pending following the October 8 work session.
The same Water Management agenda includes a separate proposed construction award of up to $5,137,531 to Carolina Civilworks Inc. for the Duke University Road/North Driver Street waterline replacement, with a proposed $513,753 contingency. That authorization would establish a combined ceiling of $5,651,284 for the waterline work.
The McKim & Creed amendment is the larger of the two proposed water-management professional-services actions and would move the South Durham facility programme into final design, permitting and bidding.
This summary was generated by AI based on the source document and may contain errors.
Source: October 8, 2026 City Council Work Session, City of Durham Department of Water Management