Concord commissions trigger-based water master plan
City of Concord Water Resources Department, North Carolina · Meeting date: November 12, 2026 · Published: November 16, 2026
Concord City Council has authorised negotiations with Hazen and Sawyer for a 2026-2027 water-system master plan, intended to translate growth, system testing and demand forecasts to 2055 into a phased capital improvement programme. The $476,000 assignment follows a wider move to update infrastructure data and assess pressure, fire-flow, storage and supply needs.
Key points
- Council authorised the City Manager to negotiate and execute a contract with Hazen and Sawyer capped at $476,000 for the 2026 Water System Master Plan.
- The consultant will rebuild the hydraulic model from current GIS data, conduct calibration and fire-flow testing, and assess existing and future water-system performance.
- Demand forecasts will run through 2055 and will consider development requests, industrial growth, wholesale supplies and water demand in each pressure zone.
- The resulting capital improvement plan will use defined demand, development and service-performance triggers to phase major transmission, pumping and storage investments over 20 years.
- Hazen anticipates completing the master plan by the end of August 2027, subject to timely data, reviews and field testing.
Full report
Concord has set out to turn its next water master plan into a trigger-based capital programme, authorising the City Manager to negotiate and execute a contract with Hazen and Sawyer worth up to $476,000.
The 2026-2027 Water System Master Plan will update the city’s hydraulic model and test its performance against current infrastructure, demand and operating conditions. More importantly, it will produce a 20-year implementation programme in which major investments are advanced when defined demand, development or service thresholds are reached rather than solely against fixed dates.
Hazen will rebuild the model directly from Concord’s current GIS network data, incorporating assets added since the last system-wide update, including the Poplar Tent booster pump station and New Midland Tank. The work will also revise pump-station and pressure-reducing-valve controls using SCADA records and operator interviews, distribute the most recent 12 months of billed consumption across model nodes, and reconcile non-revenue water with production and purchased-water records.
Field work will underpin the revised model. The programme includes four hydraulic grade-line tests on major transmission mains, 20 fire-flow tests, tests of finished-water pumps at the water treatment plant and pumps at the Corban and Rocky River booster pump stations, up to eight C-factor tests, and in-situ testing of water-treatment-plant master meters. Hazen will use the results to calibrate the model and identify discrepancies that could indicate issues such as closed valves for city staff follow-up.
The plan will forecast water demand through a 2055 design year by pressure zone. Its assumptions will draw on Cabarrus-Rowan Metropolitan Planning Organization population and employment projections, Water and Sewer Authority of Cabarrus County and city planning forecasts, historical production and use trends, development requests and land use. The scope also specifies consideration of growth associated with The Grounds, data centres and other major industrial developments, unserved population in the 890 and Midland pressure zones, and wholesale supply commitments and inter-basin transfer agreements.
Hazen will evaluate the existing and future network under a range of conditions, including pressure-zone changes, fire flow, storage, pumping capacity, supply reliability, tank operation, water age and storage turnover. It will also prepare an available-fire-flow analysis for ISO/Verisk, assessing hydrant flows while maintaining a minimum 20 psi at customer services.
The resulting capital improvement plan is to include planning-level cost estimates and project sheets for recommended improvements, including major transmission, pumping and storage schemes. Project triggers may include maximum-day demand reaching a defined share of pumping or supply capacity, development milestones at The Grounds, or deficient pressure and available fire flow. The plan will prioritise projects using hydraulic performance, regional demand, cost, risk, resilience and project benefits.
The council also authorised a separate $402,477.50 design contract with Garver for structural rehabilitation and sludge-collection improvements at the original sedimentation basins at Coddle Creek Water Treatment Plant. That assignment will assess basin movement, repair concrete deterioration and leaking joints, modernise electrical components and evaluate replacement sludge-collection equipment.
Hazen was the only respondent after Concord extended the qualifications solicitation because of an initial lack of responses. The firm anticipates completing the master plan by the end of August 2027, contingent on city data, reviews and field-testing conditions.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council Regular Meeting, City of Concord Water Resources Department