Sarpy wastewater expansion advances as EPA reviews right-of-way costs
Sarpy County and Cities Wastewater Agency, Nebraska · Meeting date: November 18, 2026 · Published: November 19, 2026
The Sarpy County and Cities Wastewater Agency expects geotechnical drilling to begin the following week on its southern Springfield line as it works through design, permitting and easement acquisition for phases 1B and 2. An EPA request for an independent review of the Midwest Right of Way contract has added a further step to the land-access process.
Key points
- Geotechnical-boring staking was completed except for one property on the southern Springfield line, with drilling expected to start the following week.
- Environmental assessments for the phase 1B southern line were complete except for one property subject to a hunting lease.
- EPA requested an independent review of the Midwest Right of Way contract to confirm that its service costs are in line with expectations.
- The board approved November claims including $43,383 for right-of-entry services and $47,015 for SCADA equipment and software.
Full report
Sarpy County and Cities Wastewater Agency is moving its phases 1B and 2 wastewater expansion through the next stages of field investigation and environmental clearance, although easement access and federal review of its right-of-way services remain active issues.
Project engineer Jeff Thompson told the board on 18 November that design activity had been limited in the short period since the previous meeting, but that environmental and geotechnical work was advancing. Staking for geotechnical borings on the southern Springfield line had been completed except at one property, and a drill rig was expected on site the following week.
Environmental assessments for phase 1B's southern line were also complete apart from a single property. The owner had allowed agency representatives to work around the fringes of the site but had not yet provided access to the property itself because of a hunting lease.
The agency is continuing to provide information to EPA as part of the easement-acquisition process. Thompson said the latest federal request was for an independent review of the Midwest Right of Way contract, recently approved by the board, to establish whether the costs were in line with those expected for such services.
The board approved its November claims report, which included a $43,383 invoice from Midwest Right of Way Services for right-of-entry services, including $43,200 for the work and $183 in mileage. It also approved a $47,015 payment to Electric Pump for SCADA equipment and software.
Financially, the agency reported $201,333 in engineering-design spending year to date through October, including phase 1B and 2 design fees and construction-manager-at-risk pre-construction services. Total cash was $14.6 million at 31 October. The agency's total loan balance was reported at $95.4 million, after a $34,000 WIFIA draw during October.
Administrator Dan Hoins said the agency would seek to retain a $4.9 million appropriation previously included for its project by Congressman Bacon, through outreach to Congresswoman-elect Denise Powell.