Monett cuts $4.35m from WWTP upgrade as budget forces scope reset
City of Monett, Missouri · Meeting date: November 12, 2026 · Published: November 17, 2026
Monett City Council has approved two change orders for its wastewater treatment plant improvements contract with McClanahan Construction Co. The action confirms a sharply reduced project scope and moves the contractual completion date to 31 January 2027 at no additional cost.
Key points
- Change Order No. 1 reduced the contract by $4,350,125, from $9,307,125 to $4,957,000.
- Work at the administration building, primary clarifiers and old digester complex was removed because of budgetary constraints.
- Improvements at the aeration basins, filter building and electrical building remain in the project scope.
- Change Order No. 2 grants a 90-calendar-day extension to 31 January 2027, with no cost adjustment.
- The council approved both change orders after staff said documentation of council approval for the first change order could not be located.
Full report
Monett City Council has approved a $4.35 million reduction in the scope of its wastewater treatment plant improvement programme, formally bringing the McClanahan Construction Co. contract down from $9.307 million to $4.957 million after the original project price exceeded the city’s budget.
The council approved Change Orders No. 1 and No. 2 on 12 November. The first order, dated August 2025, removed all work at the plant’s administration building, primary clarifiers and old digester complex. It also removed drawings 21-27 and 47-93 from the project and modified several remaining line items.
The Utilities Superintendent told the council that staff and the project engineer had reduced the project scale because the price submitted was “well higher than what we had budgeted for.” Work at the aeration basins, filter building and electrical building remains as bid.
The revised base bid is $4.507 million, supplemented by a $450,000 alternative item, for a total revised contract value of $4.957 million. McClanahan Construction Co., of Rogersville, Missouri, is the contractor; Allgeier, Martin & Associates is identified as project engineer.
Council’s resolution also regularised the approval of the first scope change. City staff said the change order had been signed, but documentation showing a council approval could not be located. The project itself had already been authorised by the council and was described during the meeting as nearly complete.
The second change order, dated 16 October, extends the contract period by 90 calendar days, setting a new completion date of 31 January 2027. It carries no cost adjustment. The Utilities Superintendent said the extension was needed to ensure there was sufficient time to finish the work and meet the requirements associated with the project’s Missouri Department of Natural Resources financing.
Before approving the resolution, the council removed an unrelated clause concerning parking and potential events in the City Hall auditorium. The amended resolution then passed unanimously.
The decision leaves Monett with a smaller but still substantial wastewater plant package concentrated on process and electrical assets, while deferring improvements to the administration building, primary clarifiers and old digester complex.