Belle Plaine starts CMAR procurement for $28m-$34m wastewater upgrade
Belle Plaine, Minnesota · Meeting date: November 16, 2026 · Published: November 17, 2026
Belle Plaine City Council has authorised the solicitation of a construction manager at risk for improvements to its wastewater treatment facility, which is at or nearing capacity. The project is listed for $8.77 million of Point Source Implementation Grant support and $22.56 million of Clean Water State Revolving Fund financing.
Key points
- Council approved Resolution 26-140 on its consent agenda, authorising Bolton & Menk to issue and administer the CMAR request for proposals.
- The planning-level construction budget is $28 million-$34 million; the state’s FY2027 project list carries a $31.325 million total cost.
- Minnesota’s intended-use plan identifies $8.768 million in PSIG funding, about 21% of total project cost, alongside $22.556 million in CWSRF loan financing.
- The works are intended to replace aging infrastructure, reduce reliance on the emergency backup pond system and meet current and future permit requirements.
- A CMAR selection is anticipated in January 2027, with a guaranteed maximum price to return to council separately after preconstruction and trade bidding.
Full report
Belle Plaine has moved into procurement for a major wastewater treatment facility upgrade after the city council authorised a request for proposals for a construction manager at risk (CMAR).
The council approved Resolution 26-140 as part of its November 16 consent agenda, allowing consulting engineer Bolton & Menk to issue and administer the procurement. The city’s wastewater treatment facility is at or nearing capacity and requires upgrades and repairs to maintain reliable operations and meet regulatory requirements.
The current planning-level construction budget is $28 million-$34 million. Minnesota Public Facilities Authority’s final FY2027 Clean Water State Revolving Fund intended-use plan lists Belle Plaine’s project at $31.325 million, comprising an $8.768 million Point Source Implementation Grant and $22.556 million in CWSRF loan financing. The grant allocation represents approximately 21% of the listed project cost.
Belle Plaine operates its own treatment facility rather than participating in the Metropolitan Council Environmental Services system. The programme is intended to replace aging infrastructure, reduce reliance on the emergency backup pond system and provide long-term treatment capacity capable of meeting current and future permit requirements.
Major elements identified for the project include a main lift station, preliminary treatment, oxidation ditches, clarifiers, ultraviolet disinfection, process and electrical improvements, new buildings, site utilities and a new outfall. Construction documents based on March 2025 designs have received agency approval, although the next phase will review and rescope the improvements against the city’s priorities and available funding.
Under the CMAR approach, the selected firm will develop cost estimates, assess constructability, phasing, scheduling and material availability, identify value-engineering opportunities, and plan competitive trade packages. Following trade-contractor bidding, the CMAR will submit a guaranteed maximum price for separate council consideration. The council may approve, seek revisions to or reject that price before authorising construction.
Bolton & Menk is scheduled to evaluate proposals and conduct interviews in December, with CMAR agreement negotiations and a council award anticipated in January 2027. Preconstruction services are anticipated for February and March, followed by council consideration of the guaranteed maximum price and construction authorisation in April.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council Meeting, Belle Plaine