Saginaw adds $731k after water main clashes with mislocated combined sewer
City of Saginaw Public Services Department, Michigan · Meeting date: November 9, 2026 · Published: November 10, 2026
City Council approved an increase taking Lois Kay Contracting’s 2026 Local Road Millage Resurfacing and Water Main Replacement contract to $3.71 million. The extra work follows an alignment change required to maintain EGLE-required separation between a new water main and the existing combined sewer.
Key points
- Council approved a $730,736.65 increase to Lois Kay Contracting’s contract, lifting its total value to $3,706,876.05.
- Excavation on Arthur Street and Maple Street found the combined sewer was one to two feet from the position indicated on existing plans.
- The water-main alignment was moved north on Arthur Street and east on Maple Street to achieve required separation from the combined sewer.
- The reroute required removal and replacement of curb and gutter, alongside additional driveway, sidewalk, pavement, aggregate-base and turf work.
- Water operations and maintenance funds provide $573,647.10 of the increase, with smaller contributions from sewer, major-street and local-street funds.
Full report
Saginaw City Council has approved a $730,736.65 contract increase for water-main replacement works after field conditions on two streets required the city to move the new main away from an existing combined sewer.
The increase takes Lois Kay Contracting Co.’s contract for the 2026 Local Road Millage Resurfacing and Water Main Replacement project to $3,706,876.05, from the $2,976,139.40 approved in June.
During excavation for the new water main on Arthur Street and Maple Street, the city found that the existing combined sewer was not in the location shown on its plans. The sewer was one to two feet from the mapped alignment. To comply with Michigan Department of Environment, Great Lakes, and Energy separation requirements, the city moved the water main farther from the sewer—north on Arthur Street and east on Maple Street.
The alignment change brought the installation closer to curb and gutter that had originally been expected to remain in place. The city said those sections must now be removed and replaced to enable the work. The revised scope also increases quantities for concrete curb and gutter, driveway approaches, sidewalk repairs, hot-mix asphalt pavement repairs, aggregate base and turf establishment.
Additional costs also reflect as-built quantity differences for ADA sidewalk ramps, road repairs before paving and asphalt paving.
The Water Operations and Maintenance Fund will supply $573,647.10 of the approved increase. The remaining funding comprises $96,758 from the Local Street Fund, $35,536.33 from the Sewer Operations and Maintenance Fund, and $24,795.22 from the Major Street Fund.
Council approved the amendment as part of its consent agenda. The decision keeps the water-main replacement programme moving while addressing a direct conflict with the existing combined-sewer infrastructure and the required potable-water separation.