New Orleans readies first citywide phase of $1bn-plus lead-line programme
Sewerage and Water Board of New Orleans, Louisiana · Meeting date: November 11, 2026 · Published: November 17, 2026
The Sewerage and Water Board of New Orleans plans to complete its first 1,500 lead service line replacements by July 2027 as it begins a phased programme expected to cover about 85,000 lines. The utility has secured or is pursuing $152 million in State Revolving Fund financing and will replace qualifying private-side lines at no cost to property owners.
Key points
- SWBNO estimates its lead service line replacement programme will cost more than $1 billion and must be completed by 2037.
- The initial target is 1,500 replacements by July 2027, followed by 7,500 additional replacements by July 2028; 28,000 inspections are targeted in the first two years.
- The utility has secured $86 million in State Revolving Fund loans and has $66 million pending, while seeking further funding.
- Hollygrove and the Upper Ninth Ward are among the first areas for canvassing and inspection work; major contracts were expected to be advertised in November 2026.
- An Attorney General opinion and Louisiana’s Amendment 7 provide the legal pathway for SWBNO to use public funds for private-property replacements.
Full report
The Sewerage and Water Board of New Orleans (SWBNO) is preparing to move its lead service line replacement effort into a larger construction phase, with an initial target of 1,500 replacements by July 2027 under a citywide programme estimated at more than $1 billion.
The utility expects that as many as 85,000 service lines could be covered by the federal Lead and Copper Rule requirements. Its stated objective is to remove all lead lines by the 2037 deadline. After the first 1,500 replacements, SWBNO plans to complete a further 7,500 by July 2028, while undertaking 28,000 inspections in the programme’s first two years.
The rollout is being structured around inspection and replacement contracts. Inspection work will establish a verifiable record of service-line material, while replacement contracts will cover locations where lead is found. SWBNO said its first large-scale contracts were expected to be advertised in November, with contracts anticipated in the first quarter of 2027.
Hollygrove is the first major canvassing area, covering about 800 properties. Canvassing began on 19 October, with contractors expected to begin inspection and replacement activity in early 2027. The Upper Ninth Ward is next, beginning with District D, where canvassing was due to start during the week of 9 November. Westbank/Algiers and Freret/Uptown are also included in the initial schedule.
A central element of the programme is SWBNO’s ability to replace private-side service lines without charging property owners. The utility said it had secured an Attorney General opinion on the use of public money for private service-line replacements, alongside the legal authority created through Amendment 7. Property owners must sign a right-of-entry form before work can take place on private property; tenants cannot execute the form.
The utility has $152 million of State Revolving Fund financing in hand or pending: $86 million in loans has been secured and $66 million is pending. It is also exploring additional funding sources. SWBNO said it would seek the remaining State Revolving Fund funding available in Louisiana.
The programme has already completed 315 residential replacements through smaller contracts and replaced service lines at 19 schools. All school replacements are expected to be completed by the end of 2027. SWBNO has also distributed more than 4,700 lead-certified water-filter pitchers since 2024 to customers with lead or unknown service lines.
The utility is using a prioritisation model with 17 factors, including the concentration of children and elderly residents, special-care facilities, social vulnerability and WIC recipients. A 47-home hydrovac inspection pilot in Gentilly was completed in early October, ahead of schedule, and will inform the wider rollout.
This summary was generated by AI based on the source document and may contain errors.