New Orleans seeks $90m state loan for lead-line replacement
Sewerage and Water Board of New Orleans, Louisiana · Meeting date: November 18, 2026 · Published: November 19, 2026
The Sewerage and Water Board of New Orleans has authorised a $90 million state revolving-fund loan application for lead service line work at its Carrollton water system. The financing push comes as the utility begins procuring replacement and inspection contracts for a programme estimated at more than $1 billion over 10 years.
Key points
- The board approved a $90 million application to Louisiana Department of Health's Drinking Water Revolving Loan Fund for lead service line identification and removal in the Carrollton Water Works and Distribution System.
- SWBNO said its citywide programme must identify and replace about 85,000 lead service lines by 2037 and is expected to exceed $1 billion.
- The utility has secured more than $152 million for the programme and plans to advertise its first inspection and replacement contracts in November.
- Construction is expected to begin in some areas in early 2027; the FY2027 capital budget includes $105 million for the lead service line programme.
Full report
The Sewerage and Water Board of New Orleans (SWBNO) has approved a $90 million application to the Louisiana Department of Health's Drinking Water Revolving Loan Fund (DWRLF), adding a potential financing source for the utility's citywide lead service line identification and removal programme.
The application seeks to place the Carrollton Water Works and Distribution System project on the state's Comprehensive Priority List. The board authorised its chief financial officer to submit the application and act as official project representative.
The financing request coincides with the transition from planning and outreach to procurement and construction. SWBNO said it would advertise two initial contracts during November: one for replacement work, including inspection and replacement when lead is found, and another for inspections intended to identify lead lines and improve the utility's predictive modelling. Construction is expected to start in some areas in early 2027.
The programme is federally mandated and aims to identify and replace approximately 85,000 lead service lines by 2037. SWBNO has estimated the work will exceed $1 billion over 10 years, although it said the estimate would be refined as it obtains more data on the large number of service lines with unknown material.
The utility reported that it has secured more than $152 million in state loans for the programme and is continuing to pursue further favourable-rate state financing. Its proposed FY2027 capital budget allocates $105 million to lead service line work, within a $479.5 million system-wide capital programme. Of that capital requirement, SWBNO identified $284 million in external funding and $174 million, or 36%, as unfunded.
SWBNO has begun canvassing in different parts of the city, collecting right-of-entry forms and carrying out initial pipe checks. It said approximately 3,000 signed right-of-entry forms had been received, including 2,000 within the first 24 hours after annual service-line inventory notices were mailed. The utility also plans community outreach before work begins in particular areas.
The board's Executive Director said the recent passage of Amendment 7 and an Attorney General opinion provided legal support for using public funds on private property. The DWRLF application notes that federal Bipartisan Infrastructure Law funding for eligible lead-service-line projects requires replacement of both public and private portions of a line, unless one portion has already been or is being replaced through another funding source.
The loan application was approved alongside three infrastructure change orders. These included a $2 million, 365-day extension for CMG Pipelines' gravity-flow sanitary sewer restoration contract, taking its value to $17.65 million and its proposed completion date to January 11, 2028.