Dodge City renews $3.14m Jacobs wastewater O&M deal as lagoon works advance
City of Dodge City, Kansas · Meeting date: November 16, 2026 · Published: November 17, 2026
Dodge City commissioners have approved a $3.139 million 2027 operating agreement with Jacobs Project Management Co. for the city’s wastewater plants, biogas facility and sewer lift stations. The action came alongside a $545,835 change order to replace failing anaerobic-lagoon outlet pipes.
Key points
- Jacobs will operate and maintain Dodge City’s South Treatment Plant, North Treatment Plant, biogas facility and sewer-system lift stations through 2027 for a $3,139,090 base fee.
- The 2027 fee is $74,658 higher than the 2026 amount.
- Commissioners also approved a $545,835.13 change order with Utility Contractors Inc. for new 18-inch outlet piping from anaerobic lagoons 1 and 2 and a connection to Aeration Basin 1.
- The lagoon-pipe work will be added to the State Revolving Fund loan for the wastewater treatment plant expansion.
Full report
Dodge City has approved a $3.139 million amendment to retain Jacobs Project Management Co. for operation, maintenance and management of its wastewater assets during 2027, as the city addresses deteriorating process infrastructure at its treatment works.
Amendment No. 6 continues Jacobs’ responsibility for the South Treatment Plant, North Treatment Plant, biogas facility and all lift stations associated with the municipal sewer system from January 1 to December 31, 2027. The base fee is $3,139,090, up $74,658 from the 2026 calendar-year amount. The commission approved the amendment unanimously.
The agreement sets annual limits of $300,000 for gypsum acquisition and application, $500,000 for repairs, $17,500 for biosolids costs and $31,844 for chemicals used at the membrane plant. Jacobs must provide accounting and invoices for expenditure above the relevant limits, while unused amounts below the gypsum, repairs and chemicals limits are to be rebated to the city under the amendment.
At the same meeting, commissioners unanimously approved Change Order No. 32, worth $545,835.13, to Utility Contractors Inc.’s guaranteed maximum price contract for the wastewater system expansion. The work covers replacement outlet pipes from anaerobic lagoons 1 and 2 and a pipe connection to Aeration Basin 1 as part of the reconstruction of Splitter Box No. 2.
The city said the existing splitter box, located between the two anaerobic lagoons and aeration basins 1 and 2, had deteriorated over roughly 40 years of operation and could no longer operate at its original capacity. In late 2025, the outlet from Anaerobic Lagoon 1 ceased allowing flow. Jacobs crews and Utility Contractors attempted to clear the obstruction, but flow stopped whenever a high-volume air hose was no longer used.
The approved work abandons the existing outlet line and installs new 18-inch PVC piping. Anaerobic Lagoon 2 is also to receive a new outlet because it has begun showing signs of restricted flow. The city said high water levels in either lagoon can back liquid into the biogas collection system and Gas Handling Building No. 1, stopping biogas production and requiring a major clean-up by Jacobs crews.
Of the change-order total, $299,377.15 relates to the completed Anaerobic Lagoon 1 tie-in, while $246,457.98 covers the Lagoon 2 tie-in and the connection to Aeration Basin 1. The cost will be added to the State Revolving Fund loan supporting the wastewater treatment plant expansion, with staff noting that some project contingency funds remain available.
This summary was generated by AI based on the source document and may contain errors.
Source: City Commission, City of Dodge City