Charlestown certifies WRF completion but keeps $1.04m back for equipment defects
City of Charlestown, Indiana · Meeting date: November 19, 2026 · Published: November 20, 2026
Charlestown Sanitary Sewer Board approved substantial completion of its $41.7m Water Reclamation Facility project on 19 November, despite unresolved problems with Clarifier No. 1 and the plant's compressed-air mixing system. Pace Contracting must provide corrective-action plans within five days and complete corrections within 30 days under formal defective-work notices.
Key points
- The board approved substantial completion for the City of Charlestown Water Reclamation Facility, establishing 19 November 2026 as the contractual substantial-completion date.
- A no-cost Change Order No. 8 added 49 days to substantial completion and 61 days to final payment, now set for 31 December 2026; the contract price remains $41.7258m.
- Formal defective-work notices require Pace Contracting to address repeated Clarifier No. 1 shear-pin failures and oil leakage affecting both compressors in the large-bubble mixing system.
- The board approved release of $1.040m, half of retained funds, while retaining a further approximately $1.04m to cover outstanding defects and remaining work.
Full report
Charlestown’s Sanitary Sewer Board has certified substantial completion of the city’s Water Reclamation Facility project, but the closeout will proceed with formal corrective obligations for key treatment equipment and more than $1m still held in retainage.
The board approved the final certificate of substantial completion on 19 November for all work under the project, delivered by Pace Contracting. The certificate sets that date as substantial completion and begins the contractual correction period and applicable warranties. It does not accept work that fails to meet contract requirements.
The facility’s contract price stands at $41.7258m, following $1.8478m of previously approved change orders. The board also approved Change Order No. 8, a no-cost extension moving substantial completion from 1 October to 19 November and the final-payment date from 31 October to 31 December.
The certificate incorporates a punch list and two notices of defective work. The first concerns Clarifier No. 1, an 85ft-diameter Ovivo circular clarifier. Its drive shear pins have repeatedly failed, including after the pins were upsized. The city directed Pace to investigate whether excessive mechanical loading, incorrect pin selection or installation, or coordination of the drive-protection system is responsible. Clarifier No. 2 is operating properly.
Pace must submit a written investigation and corrective-action plan within five calendar days, followed by correction or replacement of defective pins, assemblies, controls or contributing components within 30 days. The contractor must then demonstrate reliable operation and proper alarm and cutout functions.
The second notice addresses the large-bubble compressed-air mixing system, which comprises two 25hp Atlas Copco oil-injected rotary screw compressors. Compressor No. 1 developed significant oil leakage soon after start-up and has been held out of service pending supplier clearance, while Compressor No. 2 began exhibiting significant leakage in September. The notice says the defects compromise the specified fully redundant compressed-air system and risk continued basin mixing.
Pace must provide a corrective plan within five days and restore both compressors and the system’s specified redundancy within 30 days. Required closeout includes manufacturer-supervised verification, documented operation of each compressor and the integrated mixing system, and a 72-hour operating test at maximum basin water level.
The board approved a partial retainage release of $1.040m through two SRF disbursement requests, while leaving approximately the same amount in retainage. Project representatives said the retained sum was more than adequate for the outstanding work and the estimated replacement value of the compressors. The board was advised that all READI grant funds had been expended, with the retainage-release requests closing out that funding stream.
The facility’s October operators’ report stated that treatment remained stable and compliant with all reported permit parameters. Average influent flow was 0.514mgd, or 16% of the plant’s 4.0mgd design average.
This summary was generated by AI based on the source document and may contain errors.
Source: Sanitary Sewer Board, City of Charlestown