Danville advances $3.23m downtown sewer rehabilitation from 2029 plan
Danville,city of, Illinois · Meeting date: November 17, 2026 · Published: November 18, 2026
Danville City Council has unanimously awarded Cross Construction the Downtown Phase 1 Sanitary Sewer Rehabilitation contract, funded from sanitary sewer reserves. The project had been programmed for FY2029-30 but is now being moved into the FY2026-27 budget.
Key points
- Cross Construction received the $3,233,029.61 Bid 806 contract for Downtown Phase 1 Sanitary Sewer Rehabilitation in a unanimous 13-0 vote.
- The works respond to inflow and infiltration and structural defects identified by the 2023 Downtown Sanitary Sewer Evaluation Study.
- Danville will amend its FY2026-27 budget, increasing the infrastructure-improvements line by $3.23 million from Fund 402 sanitary sewer reserves.
- The resolution permits a purchase-order increase of up to 10% for field conditions, change orders or additions.
Full report
Danville City Council has accelerated a major downtown sewer rehabilitation project, unanimously awarding a $3.23 million construction contract to Cross Construction on 17 November.
The Downtown Phase 1 Sanitary Sewer Rehabilitation Program had been placed in the city’s capital improvement plan for FY2029-30. However, the city said it had been mistakenly programmed for that period and should instead have been included in FY2026-27. Council authorised an amendment to the current budget to provide $3,233,029.61 from Fund 402 sanitary sewer reserves for the works.
The scheme follows the city’s 2023 Downtown Sanitary Sewer Evaluation Study, which identified extraneous flows from inflow and infiltration, as well as structural defects requiring improvement. The resolution identifies reducing and eliminating inflow and infiltration as a priority for lowering long-term operations and maintenance costs and reducing sewer-backup risks.
During the council’s consideration of Bid 806, Alderman Doug Ahrens questioned the apparent high cost per linear foot. A staff member said downtown construction would be difficult because of the concentration of businesses. The works will also include cross-connection verification and elimination as construction progresses, which the staff member said would make the work slow.
The contract was awarded to Cross Construction as the lowest responsive and responsible bidder, with payment assigned to the city’s infrastructure-improvements account. The mayor and designees were authorised to issue the purchase order and execute the contract.
Council also authorised the comptroller to increase the purchase order by as much as 10% of the contract value where required by field conditions, change orders or additions, using the identified budget line or other appropriate budgeted line items.
The sewer award was approved 13-0, with all council members present voting in favour.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council, Danville,city of