GWA seeks $1.32m boost for PFAS well treatment as spent-carbon challenge grows
Guam Waterworks Authority, Guam · Meeting date: November 17, 2026 · Published: November 18, 2026
Guam Waterworks Authority has requested additional funding to complete GAC treatment at two Agana wells, lifting the project’s authorised amount to about $11.5 million. The utility said it expects 38 wells to require PFAS treatment and is still evaluating disposal or regeneration options for spent treatment media.
Key points
- The requested $1.32 million increase for Wells A-23 and A-25 would bring the GAC-treatment contract total to approximately $11.5 million.
- The added funds are for electrical and SCADA work needed to return the two wells to service; completion is scheduled for May 2027.
- GWA staff said GAC at the two-well installation can treat PFAS, dieldrin and other volatile organic compounds.
- The utility expects that about 38 wells will require PFAS treatment, although treatment may serve multiple wells from a single GAC system.
- GWA is assessing regional regeneration, shipping and emerging destruction or media-regeneration technologies for spent GAC.
Full report
Guam Waterworks Authority is seeking a further $1.32 million for its granular activated carbon treatment project at Wells A-23 and A-25, as the utility develops a wider response to PFAS treatment and spent-media management across its groundwater system.
The requested increase would take the authorised construction amount for the two wells to approximately $11.5 million. GWA said the additional money is required for electrical and supervisory control and data acquisition work needed to return the wells to operation. The scheduled completion date remains May 2027.
The A-23 and A-25 installation will use one GAC system to serve both wells. Staff said the media can treat dieldrin, PFAS and other volatile organic compounds. The utility has permanent GAC treatment operating at Y-15, as well as systems at the Tumon Maui well and NAS1 airport wells. Vessels have also been installed at M-4, where disinfection work is under way, while piping work continues at D-17.
A staff member said the utility expects about 38 wells to need PFAS treatment, while noting that GWA is not necessarily planning a dedicated GAC plant at every well. Other treatment locations remain under design ahead of the current 2029 PFAS-treatment deadline.
The scale-up presents a parallel disposal issue. GWA is storing spent GAC in large sacks at several locations, covered and intended to dry before any shipment. Wet material would have to be drummed for shipping, which staff said would be more expensive.
The authority’s engineer is evaluating disposal methods, alternatives and costs under the island-wide PFAS design and mitigation work. Options include a regional regeneration facility in the Marianas that could serve GWA, the Navy and the Commonwealth of the Northern Mariana Islands; shipment off-island; systems designed to strip contaminants from GAC using another liquid; and a treatment-and-destruction system being pursued by the Navy at a naval hospital well.
GWA said it is discussing the issue regularly with military representatives through the One Guam process. Staff described spent-media disposal as a growing issue as more GAC systems enter service.
This summary was generated by AI based on the source document and may contain errors.
Source: GWA Work Session, Guam Waterworks Authority