Fayette County pairs Beverly Manor water-main renewal with culvert works
Fayette County Utility Services, Georgia · Meeting date: November 12, 2026 · Published: November 16, 2026
The Fayette County Board of Commissioners has authorised a $626,917.50 task order to replace nearly 4,000ft of ageing 6-inch water main in Beverly Manor subdivision. The work will be delivered alongside a separate SPLOST-funded culvert replacement programme.
Key points
- Shockley Plumbing will deliver Task Order 27-14 under Fayette County's water distribution and stormwater infrastructure on-call contract, for a not-to-exceed $626,917.50.
- The programme covers 3,960ft of 6-inch ductile-iron pipe on Deerfield Lane, Ponderosa Drive, Tall Pine Drive and Ginger Cake Trail.
- Works include 11 6-inch gate valves, five hydrants, service-line work and road crossings; substantial completion is required within 180 calendar days of notice to proceed.
- Funding combines a $326,918 transfer from the Lake Horton Trail Rebuild CIP project and $300,000 from a 2017 SPLOST Category IV stormwater project.
Full report
Fayette County has approved a $626,917.50 programme to renew water distribution infrastructure in the Beverly Manor subdivision, synchronising the work with eight previously approved stormwater culvert replacements.
The Board of Commissioners authorised Task Order 27-14 for Shockley Plumbing under the county's Water Distribution and Stormwater Infrastructure Annual On-Call Contract. The task order carries a not-to-exceed value of $626,917.50 and requires substantial completion within 180 calendar days of a notice to proceed, with final completion due within 210 days.
The county will replace 3,960ft of 6-inch ductile-iron water main across Deerfield Lane, Ponderosa Drive, Tall Pine Drive and Ginger Cake Trail. The scope also includes 11 6-inch gate valves, two 2-inch ball valves, five hydrant assemblies, temporary water connections, service-line work and crossings at Tall Pine Drive.
Water System director Vanessa Tigert told commissioners that the county expects the culvert works to place old water infrastructure at risk. “We know from experience when you start replacing culverts, then a few weeks later after the culvert project is done, the water mains start breaking,” she said. Undertaking the pipe renewal in tandem is intended to avoid repeated construction disturbance and future emergency call-outs.
The water-main project is designed to fill gaps between five culvert work areas in Beverly Manor. County staff said the coordinated programme will upgrade water lines and associated assets within and between those sites, where ageing infrastructure could otherwise be damaged or experience service disruption during culvert construction.
Funding will be transferred into a newly established Beverly Manor Improvements project. The board approved a $326,918 transfer from the Lake Horton Trail Rebuild capital-improvement project and $300,000 from the 2017 SPLOST Category IV stormwater improvement project. County staff said Category IV funds may be used for utility improvements.
Shockley Plumbing was originally awarded the on-call water-distribution and stormwater infrastructure contract in July 2025; it has since been renewed for an additional year.
This summary was generated by AI based on the source document and may contain errors.