SFWMD awards $69.8m EAA Reservoir seepage-pump contract
South Florida Water Management District, Florida · Meeting date: November 12, 2026 · Published: November 17, 2026
Ric-Man Construction Florida has secured a 1,113-day contract to build the S-636 seepage pump station for the EAA A-2 Reservoir in Palm Beach County. The 240-cfs facility is a key enabling work for the reservoir, which is being accelerated from 2034 to 2029.
Key points
- The Governing Board approved a $69.781 million, 1,113-day contract with Ric-Man Construction Florida for the S-636 Seepage Pump Station Project.
- The station will have four 60-cfs electric pumps, with three primary units delivering 180 cfs and one retained as a spare.
- The project is the primary seepage control facility for the future 10,500-acre, 240,000 acre-foot EAA Reservoir and will return or supply water through the adjacent canal system as conditions require.
- The contract is funded by federal appropriations and was awarded following a sealed-bid process, with Ric-Man identified as the lowest responsive and responsible bidder.
Full report
South Florida Water Management District’s Governing Board has approved a $69.781 million contract with Ric-Man Construction Florida Inc. to build the S-636 seepage pump station, a critical component of the EAA A-2 Reservoir in Palm Beach County.
The 1,113-day contract covers the primary seepage-control facility for the future reservoir, a major Central Everglades Planning Project asset. Ric-Man was identified as the lowest responsive and responsible bidder following a sealed-bid procurement, which opened on 28 October. The award is supported by federal appropriations budgeted in fiscal year 2026-27.
S-636 will be a remotely operable facility with four 60-cfs electric pump bays. Three pumps will provide 180 cfs of design flow, while the fourth will be held as a spare. The works also include a gravity bypass culvert, fuel farm, trash rake and collection system, mechanical and electrical equipment, SCADA and IT systems, stilling wells, canal intake and discharge works, canal and levee realignment, riprap, revetment and filter work.
District staff said the station’s role is to manage offsite seepage effects from the reservoir. When water levels are high, it will pump seepage water from the seepage canal to the reservoir inflow-outflow canal. When adjacent properties require water supply, the facility can move water back into the seepage canal.
The station is the last component identified by staff as necessary to complete the EAA Reservoir. The wider CEPP EAA phase includes a 10,500-acre reservoir with 240,000 acre-feet of storage, feeding the completed 6,500-acre A-2 Stormwater Treatment Area for water-quality treatment before water is moved south.
The award follows a July 2025 agreement between Florida and the US Department of the Army that accelerated the EAA Reservoir schedule from 2034 to 2029 and enabled the state to build the seepage station using federal funds. The District assumed responsibility for the pump-station design in August 2025 while a project partnership agreement was being developed with the US Army Corps of Engineers. Staff said the final certified package was submitted to the Corps in August for the required federal determinations.
Construction across the reservoir programme is already under way. The District’s S-623 inflow pump station was awarded in October 2025, while US 27 bridge works and Miami Canal improvements are progressing. Reservoir embankment construction is also under way, with staff reporting that functional completion allowing water to be drawn from the Miami Canal is targeted for the end of 2029.