Sarasota splits $10m Whitaker Bayou dredging scheme with city and Army Corps
Sarasota County Utilities, Florida · Meeting date: November 18, 2026 · Published: November 19, 2026
Sarasota County commissioners unanimously approved a post-award modification to the Whitaker Bayou dredging project, separating the work at Martin Luther King Jr. Way. The county will dredge primarily south of MLK, while the city and US Army Corps of Engineers will handle the section to the north.
Key points
- The approved modification does not change the $10.012 million awarded for Whitaker Bayou through the 2024 storms programme.
- The original application contemplated dredging the full bayou, but funding requirements attached to the city’s Army Corps allocation prompted the project split.
- The City of Sarasota will work directly with the US Army Corps of Engineers on the dredging north of MLK; the county will deliver the work primarily south of MLK.
- The decision formed part of Sarasota County’s Resilient SRQ update, under which 36 infrastructure projects are progressing through environmental review, design or procurement.
Full report
Sarasota County has approved a revision to its $10.012 million Whitaker Bayou dredging project that will split delivery of the waterway work between the county and the City of Sarasota, working with the US Army Corps of Engineers.
Commissioners voted unanimously on 18 November to modify the post-award project scope without changing the funding amount awarded under the county’s 2024 storms programme. The county will be responsible for dredging primarily south of Martin Luther King Jr. Way, while the city and the Army Corps will undertake the work north of MLK.
County staff said the original application had contemplated dredging the entire bayou as one project and included Army Corps funding secured through the city. Further coordination with the city and the Corps identified particular requirements attached to that federal funding. Separating the work was therefore proposed as a way to accommodate those requirements.
Staff said the full scope included in the original application is still expected to be completed, but through separate projects rather than a single delivery package. The Army Corps funds are allocated directly to the City of Sarasota, rather than being managed by the county.
Commissioners also asked staff to ensure close coordination and clear communication with properties adjoining the works, given the changed delivery responsibilities on either side of MLK.
The Whitaker Bayou decision came during an update on Sarasota County’s Resilient SRQ recovery programme. The county has received $411.6 million in CDBG-DR funding across Hurricane Ian and the 2024 storms, of which $386.5 million has been allocated across housing recovery, multifamily housing and infrastructure programmes. Expenditure to date stands at $46.3 million.
The infrastructure programme, which includes dredging projects funded from the 2024 storms allocation, covers 36 projects. County staff said 22 projects had environmental clearance and 28 were in either design or procurement, with those stages overlapping for some schemes.
This summary was generated by AI based on the source document and may contain errors.
Source: BCC-Regular - Nov 18, 2026, Sarasota County Utilities