Pinellas shifts delayed US 19 utility work to QRC in $10m contract expansion
Pinellas County Utilities, Florida · Meeting date: November 17, 2026 · Published: November 18, 2026
Pinellas County Commissioners approved a $10 million, one-year expansion of QRC Inc.’s water and reclaimed-water repairs contract, giving Utilities a mechanism to undertake portions of the delayed US 19 utility work itself. The 4-3 vote followed objections from the FDOT project’s general contractor, which challenged the county’s characterisation of the delays and the proposed transfer of work.
Key points
- Change Order No. 4 adds $10 million and 365 days to QRC Inc.’s annual water and reclaimed-water repairs and extensions contract, raising its not-to-exceed value to $22.51 million.
- The county said it is descoping certain utility work from the FDOT project because of concerns over the contractor’s quality and progress, and wants greater control to expedite completion.
- Utilities said the contract will also retain capacity for emergency and unplanned water and reclaimed-water repairs; the county is not obligated to spend the full contract value.
- The board approved the change order 4-3 after Johnson Brothers, the FDOT project’s general contractor, disputed the county’s account and urged a review of the procurement approach.
Full report
Pinellas County has moved to give its utility department a separate delivery vehicle for delayed US 19 water-main work, approving a $10 million expansion and one-year extension of QRC Inc.’s annual water and reclaimed-water repair contract.
The Board of County Commissioners approved Change Order No. 4 by a 4-3 vote on 17 November. The action increases the contract by $10 million, adds 365 calendar days and takes its revised not-to-exceed value to $22.51 million.
County staff said the added capacity is needed both to allow QRC to undertake certain portions of the US 19 utility work and to restore capacity in the annual contract after previous US 19 activity depleted funds intended for other emergency repairs. The utility work had originally been included in an FDOT project, but the county cited ongoing concerns over quality and progress and said it was descoping elements of the FDOT arrangement to complete utility relocation through its own contractor.
Utilities director Jeremy Wall described the QRC arrangement as an emergency and unplanned repair contract for water and reclaimed-water infrastructure, rather than a contract dedicated solely to US 19. He said such contracts use bid unit prices for defined work, alongside time-and-materials provisions for unforeseen work.
A key immediate issue is a leaking 36-inch valve on US 19 at Evans Road, connecting a feeder main to the booster station north of Countryside Mall. Wall said the valve had been leaking for years and that the county had sought to repair it while the roadway was under construction. He said the work must begin within 30 days to avoid further delay to the road project, which is already more than 800 days behind schedule.
Johnson Brothers, the general contractor on the FDOT project, challenged the county’s approach during public comment. Its representative said the firm had raised utility-design problems more than a year earlier, including pipe-restraint issues and a major crossing structure, and had received delayed or incomplete plan revisions. The firm said it had priced the Evans Road work at $2.6 million and questioned the proposed use of QRC, referring to a $4.5 million county figure for the scope.
The contractor requested that the county suspend the change order pending a review of bidding and procurement. County staff said the county does not hold the construction contract with Johnson Brothers; its agreement is with FDOT. Staff also said the county is using the FDOT contract’s dispute-resolution process and that the QRC capacity is required to keep utility work moving.
The QRC contract was originally awarded for $5.75 million in January 2025. It had already been increased by $5 million, while an earlier $1.76 million emergency change order funded repairs to a 48-inch water-main leak on State Road 580.
Funding for the agreement is included in Pinellas County Utilities’ Water Renewal and Replacement Fund, with future funding to be included in a proposed fiscal 2027 carry-forward amendment. The county said it is preparing a replacement annual contract structured to allow multiple contractors, rather than a single provider, to perform future water, sewer and reclaimed-water work.
This summary was generated by AI based on the source document and may contain errors.
Source: Board of County Commissioners, Pinellas County Utilities