Polk County releases $75.9m BNR package for 9 mgd wastewater expansion
Northeast Public Water System or Polk County Utilities Public Water Systems, Florida · Meeting date: November 17, 2026 · Published: November 18, 2026
The Polk County Board of County Commissioners has approved GMP Addendum No. 4 with Wharton-Smith for Phase C of the Northeast Regional Wastewater Treatment Facility expansion. The package covers biological nutrient removal and equalisation infrastructure as the county responds to growth in its northeast utility service area.
Key points
- The board approved a $75,930,310 guaranteed maximum price addendum with Wharton-Smith, Inc. under the existing CMAR agreement.
- Phase C includes biological nutrient removal tanks, a system equalisation tank, splitter box, blower building and motor control centre building.
- The Northeast Regional Wastewater Treatment Facility is being expanded from 6 mgd to 9 mgd.
- Phase C is scheduled for substantial completion 1,215 calendar days after notice to proceed and final completion 57 days later.
- A fifth and final GMP package, covering a ground storage reservoir, high-service pump station and augmentation wells, is anticipated for board consideration in spring 2027.
Full report
Polk County has authorised a $75.93 million construction package for the biological-treatment portion of the Northeast Regional Wastewater Treatment Facility expansion, moving forward a major capacity upgrade intended to serve rapid growth in the county’s northeast utility service area.
The Board of County Commissioners approved Guaranteed Maximum Price Addendum No. 4 to its construction manager at risk agreement with Wharton-Smith, Inc. The addendum covers Phase C works for the facility’s expansion from 6 million gallons per day to 9 million gallons per day.
The Phase C scope comprises biological nutrient removal tanks, a system equalisation tank, splitter box, blower building and motor control centre building. Under the approved terms, substantial completion is set for 1,215 calendar days from the notice to proceed, with final completion 57 calendar days later, or 1,271 days in total. The agreement provides for liquidated damages of $3,100 per day if the construction manager exceeds the authorised contract time, subject to approved extensions.
The county is delivering the expansion through five separate GMP phases because of the size and complexity of the project. The latest approval follows three earlier packages: a $41.64 million GMP approved in December 2024 for deep-bed filters, chlorine contact chambers, dewatering equipment and a chemical-feed building; a $30.42 million package approved in February 2025 for electrical and communications upgrades, generator replacements and conversion of the site’s medium-voltage system to low voltage; and a $50.83 million package approved in November 2025 for headworks, a return pump station and a new electrical building.
Wharton-Smith developed the Phase C GMP using 90% issued-for-bid design documents prepared by Wright-Pierce in February 2026. The contractor identified bid packages and recommended low responsive bidders for demolition, sitework, concrete, canopies, hoist systems, instrumentation and controls, electrical work and slide gates. Wharton-Smith is listed as the mechanical plant contractor.
County Manager Bill Beasley said the Phase C works would increase plant capacity incrementally while design and pricing continue on the final GMP phase. That final package is expected to include a ground storage reservoir, high-service pump station and augmentation wells, and is anticipated for board consideration in spring 2027.
The wastewater expansion is included in the county’s five-year community investment programme, with funding available in the utility capital budget.
This summary was generated by AI based on the source document and may contain errors.
Source: Board of County Commissioners (Organizational), Northeast Public Water System or Polk County Utilities Public Water Systems