Martin County adds $1.22m to Coral Gardens vacuum sewer scheme
Martin County Utilities, Florida · Meeting date: November 17, 2026 · Published: November 18, 2026
The Martin County Board of County Commissioners approved an amended FY27 capital-improvement plan for the Coral Gardens Septic-to-Sewer Project, drawing on existing sewer, grant and franchise-fee resources. The additional funding addresses underestimated restoration work and changes required during construction.
Key points
- The Coral Gardens project will use a vacuum-assisted sewer system to serve about 638 parcels.
- The scheme was estimated at $16.8 million when construction was awarded; the board approved a further $1.22 million from existing sources.
- Additional costs stem from underestimated trench repair, asphalt restoration and concrete restoration, plus vacuum-pit relocations required by field conditions.
- Funding comprises $500,000 from the CFC Sewer Fund, $120,000 remaining in FDEP grant WG113, and a $600,000 transfer from FPL franchise-fee septic-to-sewer funding.
Full report
Martin County has approved a $1.22 million funding amendment for its Coral Gardens Septic-to-Sewer Project, after construction uncovered higher-than-expected restoration requirements and the need to move vacuum pits.
The Board of County Commissioners approved the amended FY27 capital-improvement plan on 17 November. The Coral Gardens scheme is being built as a vacuum-assisted sewer system serving approximately 638 parcels.
At the time of the construction bid award, the project was estimated to cost $16.8 million. Its original financing included an $8 million Florida Department of Environmental Protection grant, $1.5 million of FPL franchise-fee funding, $1 million in state revenue-sharing funding and a $6.3 million low-interest State Revolving Fund loan to be repaid through assessments.
As work has progressed, the engineer of record's estimates for trench repair, asphalt restoration and concrete restoration proved insufficient. Multiple vacuum pits have also been relocated, or will need to be relocated, to reflect actual field conditions.
The approved amendment draws $500,000 from the CFC Sewer Fund and $120,000 in available funding from FDEP grant WG113. The remaining $600,000 will be transferred from the FPL franchise-fee fund's septic-to-sewer budget line to Coral Gardens.
Utilities and Solid Waste deputy director Jeremy Coby told commissioners the added funding would fully fund the project. He said the outstanding costs included about $900,000 for additional asphalt and road base, about $100,000 for added concrete, and roughly $200,000 for asphalt associated with moving pits from swales to roadways.
Commissioner Sarah Heard asked which future work would be affected by directing additional septic-to-sewer resources to Coral Gardens. Coby said the transfer would not affect Rocky Point or Old Palm City, but could delay the next project in line after those schemes. The amendment passed unanimously.
This summary was generated by AI based on the source document and may contain errors.