Manatee advances Southwest WRF capacity expansion with $4.95m engineering package
Manatee County Utilities Operations Department, Florida · Meeting date: November 18, 2026 · Published: November 19, 2026
The Manatee County Board of County Commissioners has increased Wade Trim's engineering contract for the Southwest Water Reclamation Facility expansion to $18.64 million. The latest approval funds construction management, resident engineering support, start-up and close-out services for the move to 18mgd.
Key points
- A $4.95 million change order lifts Wade Trim's not-to-exceed engineering agreement for the Southwest Water Reclamation Facility expansion to $18.64 million.
- The expansion is intended to raise rated treatment capacity from 15mgd, currently limited to 13.5mgd, to 18mgd.
- The engineering package includes $1.68 million for construction engineering, $1.29 million for construction management and administration, and about $999,000 for resident project representative support.
- The board also transferred $2.108 million from Sewer Facility Investment Fees reserves to fund design and associated overhead costs.
- Separate approvals committed $2.69 million to rehabilitate storage pond stations, pumps and electrical panels at the same facility.
Full report
Manatee County has authorised a further $4.95 million of construction-phase engineering services for the expansion of its Southwest Water Reclamation Facility (SWWRF), taking Wade Trim's not-to-exceed contract value to $18.64 million.
The approval covers Change Order No. 3 to the professional engineering services agreement for the SWWRF expansion to 18mgd. The project is intended to increase the plant's rated capacity from 15mgd — currently limited to 13.5mgd — to 18mgd.
The new engineering scope is weighted toward the delivery phase of the programme. Construction engineering services account for $1.68 million of the change order, followed by $1.29 million for construction management and administration and $998,515 for resident project representative support. Wade Trim will also provide $532,753 of start-up and training services, $187,682 for close-out services and $255,250 for miscellaneous services.
The agreement is based on a 29-month construction period and a three-month close-out period. Its scope includes preparation of permit close-out certifications, including notifications to the Florida Department of Environmental Protection for wastewater facilities or activities, and final reconciliation of construction quantities and contract modifications.
The Board of County Commissioners also adopted a budget amendment transferring $2.108 million from reserves in the Sewer Facility Investment Fees fund to the expansion project for design and associated overhead costs.
The SWWRF approvals were accompanied by two rehabilitation packages for the plant's storage pond infrastructure. TLC Diversified received a $1.94 million guaranteed maximum price for rehabilitation of Pond Stations 1 and 3, including valves, flow meters, electrical work and instrumentation and controls. A separate $754,208 guaranteed maximum price covers four submersible pumps and associated control panels at the two stations.
Together, the decisions place construction-phase delivery and supporting rehabilitation work at the centre of Manatee's latest wastewater capital approvals.