Winter Springs clears land-acquisition route for West WRF replacement
City of Winter Springs, Florida · Meeting date: November 16, 2026 · Published: November 17, 2026
A 3-2 City Commission vote authorises negotiations and, if needed, eminent-domain action for land beside the West Water Reclamation Facility. The acquisition underpins a replacement layout estimated at $66.6 million and 29 months, versus roughly $73 million and up to 43 months for more constrained alternatives.
Key points
- Resolution 2026-23 authorises the city to negotiate for Parcel 100, a 10.189-acre tract at 900 W State Road 434 owned by Los Lagos Winter Springs, LLC, and to pursue eminent domain if negotiations fail.
- The preferred Alternative 3 would acquire about 10 acres, allowing most replacement facilities to be built independently of the operating West WRF.
- Carollo’s evaluation put Alternative 3 at about $65.8 million in construction cost and $66.6 million in total anticipated implementation cost, with a 29-month schedule.
- The existing West WRF is permitted for 2.07 mgd annual average daily flow; the planned replacement would have a 1.6 mgd design capacity and provisions for future advanced wastewater treatment.
Full report
Winter Springs has taken the key land-control step for replacement of its ageing West Water Reclamation Facility, voting 3-2 to authorise acquisition of an adjacent 10.189-acre parcel and, if negotiations fail, the use of eminent-domain proceedings.
Resolution 2026-23 authorises good-faith negotiations with owner Los Lagos Winter Springs, LLC for fee-simple title to Parcel 100 at 900 W State Road 434. It also empowers city staff, the city attorney and outside counsel to make an appraisal-based offer and file condemnation proceedings if a voluntary purchase cannot be agreed.
The decision selects the so-called Alternative 3, or moderate property acquisition, as the preferred site strategy for the West WRF replacement. The concept would use about 10 acres of adjacent land, enabling most of the new treatment works to be constructed separately from the existing operating facility.
Carollo Engineers’ site analysis found the approach carried the lowest construction and operational risk of three options. It estimated Alternative 3 at approximately $65.8 million for construction and $66.6 million in total anticipated implementation cost, including estimated wetland and tree-removal costs, with an anticipated 29-month implementation schedule.
By comparison, building entirely within the present West WRF site was estimated to cost about $73 million and take approximately 43 months. That option would require extensive demolition, temporary treatment arrangements, complex sequencing and construction beside active processes. An intermediate option requiring around three acres of adjacent land was estimated at about $73.1 million and 35 months.
The West WRF, at 1000 W State Road 434, operates under FDEP permit FLA011067 and has a permitted capacity of 2.07mgd annual average daily flow. Its two packaged treatment plants date from an earlier generation of infrastructure. A 2022 condition assessment determined that both the East and West WRFs required complete replacement because of the age and condition of their equipment and infrastructure.
The East WRF replacement has progressed through final design and is under construction. Its construction manager at risk established a guaranteed maximum price of $65.85 million. Winter Springs intends to standardise processes and equipment across the two replacement plants to simplify operations and maintenance, spare-parts availability, operator training and construction.
The planned West replacement would have a 1.6mgd design capacity, meet current public-access reuse effluent requirements and include provisions for future advanced wastewater treatment. Proposed assets include new headworks, biological nutrient-removal basins, secondary clarifiers, tertiary disk filters, chlorine contact chambers, reclaimed-water pumping, auxiliary power and operations facilities.
Commissioners heard that the larger site would provide more flexibility for contractor access, staging, stormwater infrastructure and future upgrades while reducing reliance on temporary facilities during construction. Carollo said the layout could retain a buffer along the western edge and place the headworks, a principal potential odour source, farther from nearby homes.
The parcel is subject to a conservation easement and includes wetlands. The city’s engineering team said its conceptual assessment identified about six acres of wetlands across the site, while stressing that the final layout would seek to minimise impacts and retain buffers. Environmental impacts would be addressed through permitting and mitigation.
Funding for the acquisition and replacement programme is identified as State Revolving Fund loans. Staff said the land decision was needed to maintain the planning, design and financing schedule for the West WRF project.
This summary was generated by AI based on the source document and may contain errors.
Source: City Commission - Nov 16, 2026, City of Winter Springs