Ventura authorizes $188m package for water-reuse plant
Ventura Department of Public Works, Water Resources, California · Meeting date: November 17, 2026 · Published: November 18, 2026
The City Council unanimously approved the principal delivery contracts for the VenturaWaterPure Advanced Water Purification Facility, whose total project cost is now estimated at $212.9 million. The plant is intended to turn tertiary-treated wastewater into purified water for groundwater-basin injection.
Key points
- PCL Construction’s contract was increased by $159.5 million to $161.3 million to incorporate the 90%-design guaranteed maximum price; a separate $5 million contingency was authorized.
- Hazen and Sawyer will provide $8.4 million of engineering support during construction, while MWH Constructors will provide $14.0 million of construction-management services.
- The overall project estimate increased by $20.6 million from the 2025 basis-of-design estimate to $212.9 million, with staff identifying transfers from other VenturaWaterPure and Ventura Water projects to cover the difference within adopted rates.
- The facility is due for construction completion by July 31, 2030 and is intended to support drought-resilient supply as well as compliance with discharge and reuse requirements.
Full report
Ventura City Council has cleared the way for construction of its Advanced Water Purification Facility, approving an $188.1 million package of construction, engineering and construction-management authorizations for the core VenturaWaterPure asset.
The 7-0 decision on November 17 incorporates a $159.5 million construction-phase guaranteed maximum price (GMP) into PCL Construction’s existing construction-manager-at-risk contract. The amendment raises PCL’s contract from $1.74 million for preconstruction services to $161.25 million. Council also authorized a $5 million owner-held contingency, which could lift PCL’s not-to-exceed amount to $166.25 million.
The facility will treat tertiary effluent from the Ventura Water Reclamation Facility through reverse osmosis and ultraviolet advanced oxidation. The resulting purified water is intended for injection into the groundwater basin as indirect potable reuse. City staff said the project is both a drought-resilient supply measure and a means of meeting requirements including the Tertiary Treated Flows Consent Decree, the city’s NPDES permit and recycled-water policy obligations. Ventura is required to divert tertiary-treated discharge from the Santa Clara River Estuary and put it to beneficial reuse.
The council also approved an $8.39 million Hazen and Sawyer contract for engineering support during construction, with a $419,439 contingency, and a $14.03 million construction-management contract with MWH Constructors, with a $701,488 contingency. Hazen and Sawyer’s separate design agreement was extended to December 31, 2029 without additional compensation. The construction, engineering and construction-management contracts have July 31, 2030 completion dates, with authority for 90-day extensions.
The approvals come after the project’s estimated total cost rose from $192.3 million at the 2025 basis-of-design stage to $212.9 million at 90% design. Construction costs including contingency increased by $9.9 million, while construction management rose by $7.6 million. Staff attributed the construction increase principally to general requirements and indirect costs such as tax, bonds and insurance that had not been included in the earlier estimate.
To cover the $20.6 million increase, staff identified $10 million of savings from VenturaWaterPure outfall projects, $3 million released by reducing the scope of a planned wastewater storage conversion, and $7.6 million from other Ventura Water projects. Staff said these transfers keep the project within the assumptions used for water and wastewater rates approved in December 2025.
Additional potential funding includes a $50 million state revolving fund loan, which staff said could reduce debt-service costs by at least $15 million compared with bonds, a $20 million US Bureau of Reclamation grant application and a $630,000 congressional spending earmark. Staff expects to return to council in 2027 for approval of the state loan and water and wastewater revenue bonds.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council, Ventura Department of Public Works, Water Resources