Vallejo ratifies $735k alum-tank replacement at Travis AFB plant
Vallejo Public Works Department, Water Division, California · Meeting date: November 17, 2026 · Published: November 18, 2026
The City Council approved a contract modification unlocking $629,467 in federal funding and applying $105,685 in existing Travis Air Force Base true-up credits to replace a tank central to the plant's water-treatment process. The action addresses a bulging tank that staff said presents a risk of chemical release and interruption to treatment operations.
Key points
- Council unanimously approved and ratified Contract Modification P00065 with Travis Air Force Base for the alum tank replacement project.
- The project is estimated at $735,152, comprising $629,467 in federal funding and $105,685 in existing TAFB true-up credits.
- The alum tank is deteriorated and bulging; alum is used to remove impurities during water treatment.
- The work includes engineering design, seismic requirements and removal and restoration of the canopy above the tank.
- Staff expect to return after competitive bidding for a construction-contract award; construction is anticipated to begin in spring 2027 following approvals and a notice to proceed.
Full report
Vallejo City Council has approved and ratified a $735,152 agreement with Travis Air Force Base to replace a deteriorated alum tank at the City-operated water treatment plant on the base, securing federal support for an asset staff identified as an operational risk.
The unanimous consent-calendar action approved Contract Modification P00065, accepted $629,467 in federal funding and authorised the use of $105,685 in existing fiscal-year 2025-26 Travis true-up credits. It also accepted notice of intent to amend the Water Department's fiscal-year 2026-27 budget, the first of a two-step budget process.
The existing alum tank is bulging. Alum is used in the treatment process to help remove impurities from water, and staff said delaying replacement would prolong the operational risk associated with the asset. A failure could release treatment chemicals onto City property and potentially affect nearby residential properties, interrupt treatment operations and impair Vallejo's ability to meet its contractual obligations, according to the staff report.
The project estimate includes engineering design, seismic requirements and work to remove and restore the canopy over the tank. The design estimate assigns $180,000 for canopy work, although the extent of reinstallation or replacement will depend on the canopy's condition and final construction requirements.
Funding is structured in two phases. Phase one, estimated at $555,152, comprises $453,822 in fiscal-year 2025-26 federal funding and $101,330 in true-up credits. Phase two is estimated at $180,000, supported by $4,355 in remaining true-up credits and $175,645 identified in Travis Air Force Base's fiscal-year 2026-27 budget.
The City Manager signed the modification on September 30, before Council consideration, to meet the deadline attached to the prior-year federal funds. The council action ratified that execution.
Engineering staff have completed the design and are finalising bid documents. Staff expect to advertise the project in coming months and return to Council after competitive bidding to seek award of the construction contract and address any additional funding needs based on bid results and the final canopy scope. Construction is anticipated to begin in spring 2027, subject to Council approval, contract execution and issuance of a notice to proceed.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council Regular Meeting, Vallejo Public Works Department, Water Division