South Coast adds $124k to Doheny desal legal budget as Phase 2 talks continue
South Coast Water District, California · Meeting date: November 12, 2026 · Published: November 16, 2026
South Coast Water District has lifted Hawkins’ not-to-exceed amount for Task Order 6 to $514,133.27 to support finalisation of the Doheny Ocean Desalination Project’s amended and restated progressive design-build-operate-maintain contract. Directors approved the increase but pressed staff to provide a consolidated accounting of legal assignments and expenditure.
Key points
- The board approved a $124,133.27 increase to Hawkins’ Task Order 6 ceiling, taking it from $390,000 to $514,133.27.
- The additional authorisation comprises $100,000 for further Category 6 work, $5,000 in out-of-pocket costs and $19,133.27 for work undertaken in September 2026 and thereafter.
- Staff said the legal work is focused on negotiating the Phase 2 amended and restated PDBOM services contract, including project terms, conditions and participant agreements.
- The General Manager said Hawkins’ cumulative services are expected to total slightly more than $2 million, compared with a pre-pandemic estimate of $1 million to $1.5 million.
Full report
South Coast Water District has authorised a further $124,133.27 for special counsel Hawkins to continue work on the Doheny Ocean Desalination Project’s Phase 2 contractual framework, as negotiations over the amended and restated progressive design-build-operate-maintain (PDBOM) contract continue.
The approval raises the not-to-exceed value of Task Order 6 from $390,000 to $514,133.27. The amendment includes $100,000 for additional Category 6 work, estimated at about 166 hours; $5,000 in further out-of-pocket costs; and $19,133.27 for work undertaken in September 2026 beyond the original authorisation.
Staff said the assignment is intended to take the district to the Phase 2 contract award, which is expected early next year. Hawkins has been working with district staff, counsel and the project’s PDBOM team on outstanding terms and conditions. Its work also includes reviewing participant agreements involving the project’s partners, including Eastern Laguna Beach.
The board’s approval came with a demand for more transparent project-cost reporting. One director said the sequence of task orders dating back to April 2024 made it difficult to identify the total amount paid to Hawkins, the scope of each assignment and the anticipated further requirement. Another director supported the request, saying the desalination programme had been hard to follow as individual budget amendments were presented.
Staff agreed to prepare a table setting out Hawkins’ scopes, authorisations and expenditure. The General Manager said the district had begun incorporating those incremental amounts into its budget process and would provide the information in tabular form.
The General Manager added that the legal work had originally been estimated, before the pandemic, at between $1 million and $1.5 million. He said total Hawkins services were now expected to come in slightly above $2 million, citing inflation and additional work associated with developing partnership arrangements. He said templates for partner agreements had been prepared, although further review and tailoring would be required for individual partners.
The amended Task Order 6 was approved without recorded opposition.
This summary was generated by AI based on the source document and may contain errors.
Source: Board of Directors - Nov 12, 2026, South Coast Water District