Santa Maria launches $55m pond expansion as $600m wastewater compliance programme takes shape
Santa Maria Utilities Department, California · Meeting date: November 17, 2026 · Published: November 18, 2026
Santa Maria City Council has unanimously adopted its wastewater treatment plant master plan, environmental findings and financing actions for a six-pond disposal expansion. The city is pursuing up to $50 million of Clean Water State Revolving Fund support for the first project in a wider programme driven by tighter discharge requirements and a September 2034 compliance deadline.
Key points
- Council adopted the wastewater treatment plant master plan, which sets a phased planning framework through about 2060 and replaces the 1993 plan.
- The first major project is a $55 million expansion adding six percolation ponds across about 42 acres on city-owned land east of Black Road.
- Santa Maria will apply for up to $50 million in Clean Water State Revolving Fund financing, with an estimated $5 million contribution from the Wastewater Enterprise Fund.
- The city estimates the projects required to reach compliance by 2034 at about $600 million, including treatment-process upgrades and other improvements.
- The Central Coast Regional Water Quality Control Board's time schedule order requires full compliance with discharge requirements by September 30, 2034; the master plan must be approved by December 31, 2026.
Full report
Santa Maria City Council has put a $55 million percolation-pond expansion at the front of a wastewater compliance and renewal programme that the city currently estimates will require about $600 million of investment through 2034.
The council unanimously adopted the Santa Maria Wastewater Treatment Plant Master Plan, an initial study/mitigated negative declaration and related financing resolutions on November 17. The actions also authorize an application for state financial assistance and allow the city to reimburse eligible project expenditures from future State Water Resources Control Board financing proceeds.
The master plan provides a phased framework for treatment, disposal and reuse improvements through approximately 2060. It was prepared with Carollo Engineers and replaces the city's 1993 wastewater master plan. Black & Veatch completed an independent review, finding the plan consistent with current best practice and a sound framework for safe, reliable and cost-effective treatment and disposal, the Utilities Department said.
The immediate priority is the Percolation Pond Expansion Project. Santa Maria disposes of treated wastewater through percolation ponds rather than discharging to a creek, stream or other surface water. The project would add six ponds totalling about 42 acres on city-owned land east of Black Road, adjacent to the existing treatment plant at 601 Black Road. It is intended to increase disposal capacity and create space for rehabilitation of existing ponds, some of which have been in service since the 1940s.
The city will seek up to $50 million from the Clean Water State Revolving Fund towards the estimated $55 million cost, with the remaining $5 million proposed from the Wastewater Enterprise Fund. Utilities Director Shad Springer told council that the programme offers interest rates of roughly half those available through a bond issuance. The council's action authorizes an application only; any financing agreement would return for council approval.
The application is due by December 31, 2026. If successful, the city expects to learn whether it has reached the state's fundable list in late spring 2027. Staff anticipates bidding the pond project in late 2027, followed by construction between 2028 and 2030, provided financing is secured.
The planning and finance actions respond to a Time Schedule Order issued by the Central Coast Regional Water Quality Control Board in February 2026. The order followed updated discharge requirements that the existing treatment process cannot meet. It requires Santa Maria to comply fully by September 30, 2034 and to obtain approval of a wastewater master plan by the end of 2026.
Springer said the order protects the city from permit violations and associated penalties as long as it meets its milestones. The city currently cannot meet at least three permit constituents on a daily basis; he said violations can carry penalties of at least $3,000 per day per violation.
Although the plant's permitted treatment capacity is 8.3 million gallons a day and average current flow is about 6.2mgd, the city identified aging infrastructure, stronger wastewater, limited disposal capacity, anticipated growth and tighter discharge requirements as drivers for investment. The $600 million estimate covers the projects needed to reach the 2034 compliance pathway and has been escalated to reflect anticipated costs during construction. Staff said it will refine designs and costs over the next several years, and will return with funding proposals for later phases.
The council also adopted a mitigation monitoring and reporting programme as part of the environmental review. Individual future components may require further project-specific environmental work or permits.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council Meeting, Santa Maria Utilities Department