SFPUC awards $85m CMGC deal for Moccasin Dam spillway upgrade
San Francisco Public Utilities Commission, California · Meeting date: November 10, 2026 · Published: November 11, 2026
The San Francisco Public Utilities Commission has appointed Myers-Sukut Joint Venture to support design and preconstruction for a new concrete side-channel spillway at Moccasin Dam and Reservoir. The project follows a 2018 flood in which reservoir levels came within 1.3 feet of the dam crest.
Key points
- Myers-Sukut Joint Venture received the $85.085 million, 2,325-calendar-day CMGC contract after a competitive process involving three teams.
- The commission authorised $2.708 million of preconstruction services over 774 calendar days; construction requires a later commission authorisation.
- The proposed concrete side-channel spillway would replace the existing auxiliary spillway to pass the updated design flood without overtopping the dam.
- Environmental review under CEQA and approval of the final design by the Division of Safety of Dams remain under way.
- The contract carries a 12% contract-wide LBE requirement; the preconstruction proposal includes 2.99% LBE participation, with the balance planned through future construction trade packages.
Full report
San Francisco Public Utilities Commission has awarded an $85.085 million construction manager/general contractor contract for long-term improvements at Moccasin Dam and Reservoir, beginning a preconstruction phase for a new spillway intended to address flood and dam-safety risks.
The commission selected Myers-Sukut Joint Venture, comprising Myers & Sons Construction and Sukut Construction, following a competitive procurement in which three teams submitted proposals. The joint venture was ranked first after an evaluation covering qualifications, interviews, price, diversity commitments and social-impact partnership programmes.
The contract has a maximum duration of 2,325 consecutive calendar days, or about six years and four months. However, the commission's immediate authorisation is limited to $2.708 million of preconstruction services over 774 consecutive calendar days, approximately two years and one month. Those services include constructability review, cost estimating, scheduling, risk management and development of work packages during design.
The project will replace the existing auxiliary spillway with a concrete side-channel spillway and associated work. Moccasin Dam and Reservoir are part of the Hetch Hetchy regional water system. During a March 2018 flood event, reservoir levels rose to within approximately 1.3 feet of the dam crest, triggering downstream emergency evacuations and causing significant damage to the auxiliary spillway and surrounding facilities.
Following the event, SFPUC staff determined that the updated design flood exceeds the capacity of the current spillway system. The planned replacement is designed to pass that flood without overtopping the dam, according to the project presentation.
The CMGC approach brings the contractor into the design phase rather than waiting for a completed design before procuring construction. Staff said that early contractor involvement would provide constructability, cost, scheduling and work-packaging input intended to reduce construction risks and improve cost certainty.
Construction itself has not been authorised. The SFPUC environmental team and Planning Department are conducting environmental review under the California Environmental Quality Act, while the final spillway design and associated works require approval from the Division of Safety of Dams. Staff will return to the commission for construction authorisation after those reviews are complete.
The contract includes a 12% contract-wide local business enterprise requirement. The joint venture proposed 2.99% LBE participation for preconstruction services, with the remaining requirement to be met during construction through future trade packages.
This summary was generated by AI based on the source document and may contain errors.
Source: Public Utilities Commission, San Francisco Public Utilities Commission