Rainbow awards $1.86m Eagles Perch pipeline contract
Rainbow Municipal Water District, California · Meeting date: November 17, 2026 · Published: November 18, 2026
Rainbow Municipal Water District has selected MRay Engineering Incorporated to deliver the Eagles Perch Water Pipeline Improvement Project after receiving six bids. The board also authorised additional funding and construction-management support as it prepares to work along narrow residential roads.
Key points
- MRay Engineering Incorporated was awarded the construction contract on its $1,861,493.50 bid, the lowest responsive and responsible bid among six received.
- The board approved a further $297,000 appropriation for soft costs, including legal, consulting, staff and engineering support; staff said nearly $186,000 of this was construction contingency.
- Golden State Consultants was selected for construction-management services, while district staff will provide full-time inspection.
- The board approved the project unanimously after staff said the contractor had been briefed on the need for intensive customer coordination during construction.
Full report
Rainbow Municipal Water District has approved the construction award and supplementary funding needed to advance the Eagles Perch Water Pipeline Improvement Project, positioning the scheme as the utility’s leading capital priority for the year.
The board unanimously awarded the construction contract to MRay Engineering Incorporated for $1,861,493.50. MRay was the lowest responsive and responsible bidder in a field of six, following the district’s September 22 solicitation and October 20 bid opening. Staff said its review found no irregularities in the bid.
The approval also covers a professional-services agreement with Golden State Consultants for construction management and authorises the General Manager to implement both agreements. The consultant will handle submittals, progress meetings and daily customer interactions, while the district’s senior inspector will provide full-time inspection.
In parallel, directors approved a $297,000 additional appropriation for costs outside the construction contract, including legal, consulting, staff time and engineering support during design. Staff said that almost $186,000 of the request was contingency intended to administer the contract and address potential construction issues.
The spread between bids prompted questions from directors. Staff said the district had received no bid protests and that its line-item review had not identified any unusually priced element in MRay’s proposal. A staff member said the competitive bidding environment had strengthened, with contractors more actively seeking work, and described the low bid as aggressive but not abnormal.
Project delivery will require particular attention to residents because construction will take place on very narrow roads. Staff said the district had already worked extensively with affected customers and had made clear to the contractor that it expected close support during the work, including practical assistance where access is disrupted.
A director described Eagles Perch as a project that had been deferred for many years, noting that the existing pipe had previously failed. The director credited district staff with securing the easements needed for the new alignment and said the replacement was necessary to avoid another failure.
The district expects to bring further capital requests in December after bidding the Wild Acres Pump Station project and its first tank-recoating project.
This summary was generated by AI based on the source document and may contain errors.
Source: Board of Directors, Rainbow Municipal Water District