Newport Beach advances $29.6m joint groundwater well project
Newport Beach Municipal Operations Department, California · Meeting date: November 17, 2026 · Published: November 18, 2026
Newport Beach City Council has approved construction financing, land acquisition and a long-term water-delivery agreement for the Bushard Street dual-well facility. The project will be jointly funded and operated with Laguna Beach County Water District, with Newport Beach retaining a 58% capacity share.
Key points
- Council unanimously approved the Bushard Street Water Wells project as part of the consent calendar, including a $10 million OCWD well-construction loan.
- Best Drilling and Pump won the initial drilling and pipeline contract at $3.50 million, 13% below the engineer's $4.0 million estimate.
- Newport Beach will buy a 51% interest in the Fountain Valley well site for $1.40 million and receive $11.28 million in project reimbursements from Laguna Beach County Water District.
- The planned dual-well facility has an estimated initial capacity of 5,500 acre-feet a year, with Newport Beach allocated 58% and Laguna Beach County Water District 42%.
Full report
Newport Beach has moved its Bushard Street groundwater project from planning into construction, approving a package of land, financing, construction and water-delivery agreements for a jointly owned dual-well facility in Fountain Valley.
The City Council approved the measures unanimously as part of its November 17 consent calendar. Together, the actions establish Newport Beach as lead agency for design, construction and operations of the project with Laguna Beach County Water District (LBCWD), while securing an initial construction contract and a $10 million Orange County Water District (OCWD) loan.
The facility at 17902 Bushard Street is planned as a deep and shallow well system, connected to Newport Beach's existing transmission main. Staff said the wells are anticipated to produce 5,000-6,000 acre-feet of groundwater annually for the two agencies; the parties' agreement uses 5,500 acre-feet a year as its initial planning capacity.
Newport Beach will hold 58% of the initial capacity, or 3,190 acre-feet a year, while LBCWD will hold 42%, or 2,310 acre-feet a year. The city will also have first access to any unused LBCWD capacity under the agreement, subject to a capacity charge.
The project is estimated to cost $29.6 million in total. Newport Beach's share is estimated at $17.0 million and LBCWD's at $12.6 million. Council approved a $1.4025 million purchase for a 51% tenant-in-common interest in the 0.51-acre site, representing 51% of LBCWD's original $2.75 million property acquisition cost.
A budget amendment adds $11.28 million in LBCWD cost-share revenue and matching expenditure authority to project 24W13, alongside the land-purchase appropriation from the Water Enterprise Fund.
The council also awarded Best Drilling and Pump a $3.498 million contract for the first construction phase, covering new wells and pipeline work. The bid was 13% below the $4 million engineer's estimate, with a $525,000 contingency approved for unforeseen conditions. The contractor has 250 consecutive working days to complete the work, with construction scheduled to start in November following contract execution.
Richard C. Slade & Associates was approved for groundwater-development construction monitoring and field services at a not-to-exceed value of $307,589. The first-phase package, including construction, contingency, hydrogeological services and incidentals, totals $4.332 million.
OCWD's Producer Well Construction Loan Program will provide up to $10 million for Newport Beach's share of the overall effort. The loan is repayable over 20 years following substantial completion, with interest beginning at that point. During council comments, Councilmember Erik Weigand said the OCWD programme offered well loans at a 3.5% rate, which he described as less expensive than bonding.
The operating agreement makes Newport Beach responsible for operating, maintaining, repairing and managing the shared facilities. LBCWD will pay its proportional share of actual operating and maintenance costs based on delivered water. Newport Beach will convey LBCWD's allocation through approximately 12 miles of its existing system to a connection point in Corona del Mar. The agreement establishes a wheeling charge of $253.05 per acre-foot in 2028 dollars, subject to adjustment, for that use of Newport Beach infrastructure.
For Newport Beach, the project is intended to add local groundwater supply, reliability and redundancy. For LBCWD, which has imported water for its supply, the agreement creates a new uninterruptible groundwater-delivery arrangement after Newport Beach's previous intermittent deliveries of excess groundwater ended in 2020.
This summary was generated by AI based on the source document and may contain errors.
Source: City Council, Newport Beach Municipal Operations Department